Bekisopa Iron Ore Project Pre-Feasibility Study
Released
Released
Announcement PDF
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Akora Resources Limited
PO Box 28
Ballarat Victoria 3350
Australia
info@akoravy.com
ACN 139 847 555
ASX: AKO
www.akoravy.com
31 March 2025
ASX RELEASE
Bekisopa high-grade iron ore project PFS confirms a
robust 2Mtpa DSO Operation with an 86% IRR.
Highlights
•
Bekisopa iron ore project Pre-Feasibility Study (PFS) for a 2 million tonne per annum
(Mtpa) Direct Shipping Ore (DSO) operation in Madagascar confirms strong economics.
•
Average Life of Mine (LOM) Lump product grade at 62% Iron (Fe) and Fines product grade
at 61%Fe over an initial 6 year mine life, with potential to add to the DSO inventory and a
potential multi-year Stage 2 to follow.
•
Over the LOM, the operation delivers 40% Lump and 60% Fines products.
•
Start-up capital of US$60.6 million (M), including US$6.8M in EPCM costs and a 15%
contingency, with capital payback in 1.8 years from first production.
•
This investment delivers revenues of US$789M (A$1.25B), C1 cash cost of US$42/t and
pre-tax cash flow of US$310M (A$0.5B).
•
Robust financials with NPV10 of US$147*M pre-tax (A$233M) and IRR of 86%.
•
Bekisopa Maiden Ore Reserve statement confirms 9.1Mt and a low strip ratio of 0.52.
•
Pathway to Final Investment Decision in mid-2026 and first shipment in Q3 of 2027.
AKORA Resources Ltd (ASX: AKO) (“AKORA” or “Company”) has a Pre-Feasibility Study
(PFS) that demonstrates that its flagship 100%-owned Bekisopa iron ore Project in Madagascar
could produce 2Mtpa of 61.6%Fe average blended grade lump and fines iron ore products for blast
furnace steelmakers.
This Study, which enhances the Scoping Study completed by the Company in 2023, confirms that
the Bekisopa operation has a low capital cost entry case of US$60.6M and would generate a pretax cash flow of US$310M over an initial 6 year mine life from revenues of US$789M.
Other key metrics to the Bekisopa PFS, includes;
•
MRE Indicated Resource tonnage has increased to 8.5Mt @55.4%Fe from 4.4Mt @60.9%Fe.
•
Geotechnical studies show that the DSO reserve will not require drill and blasting.
•
New road route from Bekisopa to the Zomandoa River crossing surveyed to be ~25kms.
•
The Toliara town by-pass road off the RN7, National Highway, enables the existing port to be
utilised to export Bekisopa iron ore products.
•
*A review of sea freight costs for bulk cargoes, Toliara to India west coast port, has been
assessed at ~US$14/t versus US$5.5/t estimate in the Scoping Study, this reduced the NPV by
~US$35M.
1
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
AKORA’s Managing Director, Paul Bibby said:
“Since the release of our positive Scoping Study in November 2023, the AKORA team has worked
hard delivering this PFS on time. This PFS confirms that a start-up DSO iron ore operation at
Bekisopa is economically viable with strong financial, operational, environment, and product
credentials. With the release of the PFS, expectation is that potential Strategic Investors will
reengage.
We believe that further drilling will confirm additional mine life, and the vision for a many decade
high grade iron ore concentrate project beyond the initial DSO start-up phase is achievable.
The PFS shows the Bekisopa DSO project to be a robust and sustainable project based on low
operating cost at US$42/t, generates strong revenues from an accelerated production ramp-up,
reducing the projects capital payback time to just 1.8 years. Significantly improved pre-tax cash
flow of US$310M using a long-term benchmark iron ore price of US$100/t, delivers a very positive
NPV of US$147M, and an IRR of 86% from an initial capital investment of just US$61M.
Bekisopa has been identified as a Government Project of Significance1 which has the support of
the National Government and local communities. This PFS shows a pathway to a Financial
Investment Decision and first shipment in the second half of 2027.”
AKORA’s Chairman, Graeme Hunt, said:
“The excellent progress by the AKORA team in just over four years from listing and a year since
the positive Scoping Study speaks volumes to their focus and importantly the quality of the
Bekisopa iron ore resource. This PFS gives us and our shareholders the encouragement to
continue progressing Bekisopa into an operation as we focus on delivering a Strategic Investor and
funding arrangement that meets our shareholders and investor objectives.”
1
ASX Release – Mines Minister supports Bekisopa Project – 8 Oct 2024
2
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
This announcement has been reviewed and approved for release by the Competent Persons
at Wardell Armstrong International – part of SLR Consulting (WAI)
This announcement has been authorised by AKORA Resources’ Board of Directors.
For further information please contact:
Paul G Bibby
Managing Director
Phone +61(0) 419 429 833
www.akoravy.com
Gareth Quinn
Investor Relations
Phone +61(0) 417 711 108
gareth@republicir.com.au
Cautionary Statement
The Pre-Feasibility Study referred to in this ASX release has been undertaken for the purpose of evaluation of a potential development
of the Bekisopa iron ore project in Madagascar. It is a preliminary technical and economic study of the potential viability of the Bekisopa
Project. The Pre-Feasibility Study (PFS) outcomes, production target and forecast financial information referred to in this release are
based on Ore Reserve level technical and economic assessments. The Pre-Feasibility Study has been completed to a level of accuracy
of -10%/+30% in line with a PFS study accuracy. While each of the modifying factors was considered and applied, there is no certainty of
eventual conversion to Ore Reserves or that the production target itself will be realised. Given the uncertainties involved, investors should
not make any investment decisions based solely on the results of the Pre-Feasibility Study.
Of the Mineral Resources scheduled for extraction in the Pre-Feasibility Study production plan approximately 94% are classified as
Indicated and 6% as Inferred during the initial six year evaluation period. There is a low level of geological confidence associated with
Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral
Resources or that the production target itself will be realised. Inferred Resources comprise 3% of the production schedule in the first three
years of operation. AKORA confirms that the financial viability of the Bekisopa South iron ore Project is not dependent on the inclusion of
Inferred Resources in the production schedule.
The Mineral Resources underpinning the production target in the Pre-Feasibility Study have been prepared by a competent person in
accordance with the requirements of the JORC Code (2012). The Competent Person’s Statement is found on page 47 of this ASX release.
For full details of the Mineral Resources estimate, please refer to AKORA’s ASX release dated 11 April 2022 and 25 February 2025.
AKORA confirms that it is not aware of any new information or data that materially affects the information included in that release. All
material assumptions and technical parameters underpinning the estimates in that ASX release continue to apply and have not materially
changed.
This release contains a series of forward-looking statements. Generally, the words "expect," “potential”, "intend," "estimate," "will" and
similar expressions identify forward-looking statements. By their very nature forward-looking statements are subject to known and
unknown risks and uncertainties that may cause our actual results, performance or achievements, to differ materially from those expressed
or implied in any of our forward-looking statements, which are not guarantees of future performance. Statements in this release regarding
AKORA’s business or proposed business, which are not historical facts, are forward-looking statements that involve risks and
uncertainties, such as Mineral Resource estimates, market prices of iron, capital and operating costs, changes in project parameters as
plans continue to be evaluated, continued availability of capital and financing and general economic, market or business conditions, and
statements that describe AKORA’s future plans, objectives or goals, including words to the effect that AKORA or management expects a
stated condition or result to occur. Forward-looking statements rely on estimates and assumptions that, while considered reasonable by
AKORA, are inherently subject to significant technical, business, economic, competitive, political and social uncertainties and
contingencies. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks
and uncertainties. Actual results in each case could differ materially from those currently anticipated in such statements. Investors are
cautioned not to place undue reliance on forward-looking statements, which speak only as of the date they are made.
AKORA has concluded that it has a reasonable basis for providing these forward-looking statements and the forecast financial information
included in this release. This includes a reasonable basis to expect that it will be able to fund the development of the Bekisopa Project
upon successful delivery of key development milestones and when required. The detailed reasons for these conclusions are outlined
throughout this ASX release (including the Financial section of this announcement). Based on the level of pre production capital
expenditure required it is reasonable to expect that AKORA can raise the required capital funds, through a mixture of shareholder
investment, debt and equity raises. The Board has experience raising equity via capital markets. Debt may be secured through several
providers who are well versed in supplying capital for mining projects. The Company will pursue strategic partners to consider alternate
funding options which could include corporate transactions, joint venture or asset sales. There is however no certainty that AKORA will
be able to source funding as and when required to progress the project.
AKORA believes that this Announcement is a fair and balanced summary of the Pre-Feasibility Study. Given the uncertainties involved
investors should not make any investment decisions based solely on the results of the PFS.
This ASX release has been prepared in compliance with the current JORC Code (2012) and the ASX Listing Rules. All material
assumptions, including sufficient progression of all JORC modifying factors, on which the production target and forecast financial are
based. All reporting of dollar amounts and Financial are in US Dollars (US$). A US$0.63/A$ exchange rate has been used based on
March 2025 data. Production and cash costs are reported in wet metric tonnes. All resource tonnes are measured in dry metric tonnes.
Pre-Tax Cash Flow calculated as Net Revenue less Total Operating Costs.
3
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
4
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Executive Summary
The Pre-Feasibility Study (PFS) for the Bekisopa Iron Ore Project in south central Madagascar has
defined a conventional economically robust start-up direct shipping ore (DSO) strategy for a 2
million tonne per annum (Mtpa) operation with an initial six-year mine life.
Prepared by Wardell Armstrong International (WAI), a part of SLR Consulting, the PFS shows that
the Stage 1 DSO operation is economically viable with strong financial, operational, environmental,
and product credentials able to deliver a Fines product at an average LOM grade of 61.4% Iron
(Fe) and a Lump product at an average (Life of Mine) LOM grade of 61.8% Fe.
This PFS has delivered a maiden ore reserve for the Bekisopa deposit of 9.1 million tonnes (Mt) at
53.3% Fe. This provides 94% of the Mine Production Schedule; with the remainder of the Mine
Production Schedule tonnage coming from the Inferred Resource all later than the payback point
and scheduled to be mined in the latter years of the life of mine. The expectation is that future infill
drilling of known DSO mineralisation should add tonnes and therefore additional mine life, as
demonstrated from the recent drilling and infill drilling campaigns.
At US$100/t for Benchmark grade 62% iron ore, Bekisopa’s proposed DSO project has a pre-tax
Net Present Value 10 (NPV10) of US$147M with an Internal Rate of Return (IRR) of 86% from an
initial capital cost of US$60 million (including 15% contingency), with C1 cash costs of US$42/t,
and pre-tax capital payback in 1.8 years from first production. Over the life of mine, the project
delivers pre-tax cash flow of US$310M from revenues of US$789M.
The significant scale and particular mineralisation characteristics of Bekisopa’s iron ore resource
presents the Company with a staged development program:
1. Stage 1: Produce ~61.6% Fe average grade direct shipping ore (DSO): Mine, crush and
screen the at-surface ‘weathered zone’ iron ore to produce a LOM average blended grade
of 61.6%Fe across the lump and fines product for shipping to Blast Furnace-Basic Oxygen
Furnace (BF-BOF) steelmakers via a port at Toliara.
2. Stage 2: Produce +67% Fe grade Direct Reduced iron concentrate: Using cash
generated from DSO start-up production, mining the underlying fresh mineralisation and
adding grinding and magnetic separation circuits to upgrade ore to a +67% Fe low impurity
concentrate at 75 microns for shipping to Direct Reduced Iron-Electric Arc Furnace (DRIEAF) steelmakers via a port of Toliara. The DRI-EAF process is used to manufacture
greener steel with considerably less carbon emissions.
The PFS focused on a minimum capital “Low CAPEX Approach” for the Stage 1 DSO open pit
mining operation and considers using contract mining and mobile processing equipment (crushing,
screen, and with magnetic separation after Year 3), and conveying, contract truck hauling of the
product, as well as operating barges and a floating crane at the existing Toliara port.
This start-up case has a production schedule ramping up from 0.7Mtpa to 2Mtpa over three years,
one year faster than the Scoping Study. This is to ensure that management and employees are
progressively and appropriately trained to reliably mine and process product of consistent quality,
safely drive haul trucks, manage capital and operational scale-up risks and achieve improved
project reliability and economics.
5
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
The PFS, which has covered multiple activities including site and community data collection,
technical studies, road and port infrastructure surveys and iron ore-product quality assessments,
has improved the project’s scope definition and refined the capital and operational costs. The
resource definition has improved over 2024, enabling iterations of the mine plan and early
optimisation of the processing operations to deliver both lump and fines iron ore products.
Extensive discussions with contractors for mining, processing, road construction, road haulage,
port engineering and ship loading, have informed the physical and financial evaluations of the PFS.
The local communities at Tanamarina and Bekisopa are supportive of the Company and its plans
for an iron ore operation, viewing it as a significant opportunity for investment into the local
communities and providing; education, health, training, employment opportunities. People from
these local villages have been given employment opportunities and have supported the company
through the PFS process.
AKORA is working with the Madagascan Government’s Mining Ministry to confirm the pathway to
Final Investment Decision and into operation. Discussions have commenced with several key
Ministries to develop an understanding of the Bekisopa project requirements and agree
engagement protocols for the development of the project. AKORA will work with the Mines Ministry
and Madagascar Mining Cadastre Office (BCMM) to transform the existing Bekisopa tenements
into ‘Exploitation / Mining Permits’ by the end of 2025, enabling construction planning to
commence.
Figure 1. AKORA’S flagship Bekisopa Project in south central Madagascar is one of four iron ore
projects in the Company’s portfolio.
6
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Project Overview
AKORA Resources’ 100% owned Bekisopa Project is a substantial iron ore project in south central
Madagascar. Mining the at surface weathered zone iron ore, where the iron mineralisation has
been enriched, does not require drilling and blasting, just conventional truck and shovel mining
then crushing and screening to produce Lump and Fines iron products at LOM average blended
grade of 61.6% Fe. The project will create employment opportunities and the establishment of
various community beneficial projects.
Products from the Bekisopa mine will be transported by road trucks to the RN7 National Highway
which connects to the coastal port of Toliara where the iron ore products will be exported to
steelmakers, initially from the existing Toliara port facility. This PFS builds on an encouraging
Scoping Study released in November 2023 and enhances the case for a financially sustainable,
robust project.
At design capacity, the 2Mtpa production will be transported to port on public roads, of which the
first 25km from Bekisopa site will be constructed as a public – private road by AKORA.
Port capacity outside of Toliara will comprise a stockpiling area for two products, administration
and maintenance buildings and employee accommodation facilities. A plant nursery and
potentially other community project will also be established.
Figure 2. Bekisopa’s DSO resource has the potential to produce a Lump product at an average
61.8% Fe grade (left) and a Fines product at an average 61.4% Fe (right), over the PFS LOM.
7
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Environment & Social
An environmental scoping study has been developed by WAI for the Bekisopa Project and the
detailed baseline investigation activities are well progressed with the outcome being a detailed
Environmental and Social Impact Assessment (ESIA). Environmental approvals are required to
support the issuing of the exploitation permits with an environmental and social management plan
being a key control to support the sustainable operation of the project.
After four years of exploration at Bekisopa, AKORA has developed a good relationship with the
local community. Several community projects have been initiated and there is an overall
supportive attitude towards the Project. Bekisopa is well positioned in working with the national
government to advance the project into a project of national significance.
The ESIA will form the basis of defining social sensitivities and opportunities. AKORA is currently
working with the local community to upgrade the medical centre.
Water
AKORA is aware of the sensitivity of water usage on site and surrounding areas. A bore system
has been tested on site and forms the basis for the project water supply going forward. With dry
processing and no requirement for tailings dams water usage has been minimised.
Weather
As there is no historical weather data available for the Bekisopa area, a weather station was
installed at the Tanamarina village in July 2023 (see Figure 3a). The weather station captures and
records / saves all relevant weather data every 15 minutes. As a result, there is now 18 months of
actual weather data, temperature, rainfall, wind speeds etc, that can be used for mine planning
and environmental considerations for the Bekisopa Project (see Figure 3b).
a
b
Figure 3. Weather station installed at Tanamarina in July 2023 (a) has been continually capturing
all relevant weather information for the PFS (b).
8
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Temperature and rainfall weather details were recorded over the past 18 months and cover two
wet seasons at Bekisopa, being November to March. The climate at Bekisopa is ‘temperate’ with
average daily temperature of 24oC, maximum summer temperature of 38oC and winter minimum of
7oC.
A consideration for the Bekisopa Project is operating through the wet season when reasonable
daily rainfall occurs and monthly totals average around 200mm. February 2025 rainfall was
unusually high, impacted by two cyclones present over southern Madagascar during late
February. The main impact of this rainfall is the rising level of the Zomandoa River where a
crossing will be constructed. In the initial ramp up years iron ore products will be hauled across the
river in the dry season.
Tenements & Land Access
The two main Bekisopa tenements, PR10430 and PRE 3757, were submitted to the BCMM in
early March 2025 to be included in the first batch of 100 for renewal. Expectation is that these
tenements will receive renewal shortly, a significant point, and then AKORA will commence the
process of having them transformed into Exploitation (Mining) Permits over the coming months.
Figure 4. The Bekisopa Project comprises tenements PRE 3757 and PR10430.
The transition from the 100% AKORA owned exploration permits into exploitation permits to
facilitate the commencement of construction and operations are well understood and preliminary
steps are in place to progress this transition. Land access is well supported by the Mining Code
and transition of land ownership will be done in accordance with best practice and legal
requirements.
Permit and approval requirements for the construction of the new haulage road linking Bekisopa to
Satrokala are identified and planned. Land access and operating approval for the construction of
the port receival facility and use of, or construction of, the maritime port structures is identified.
Early engagement with the Ministry of Public Works and the Ministry of Infrastructure (Ports and
Maritime division) has occurred.
9
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Geology and Exploration
The Bekisopa property occurs within the Anosyen Domain and Ikalamavony sub-domain of
Madagascar. More specifically Permits PRE 3757 and PR 10430 occur within the Ihosy and
Amparihy Formations of the Akora Group (Anosyen Domain) and the Bekisopa and Betainamboa
Formations of the Ikalamavony Group (Ikalamavony Sub-domain). To the north-east and southwest of the permits are intrusions of the Ambalavao Suite (See Figure 5).
The Akora Group includes the non-felsic volcanic meta-sedimentary rocks of the Anosyen Domain.
The Amparihy Formation rocks are characterised by a distinctive and well-developed stromatic
migmatitic layering but are otherwise largely homogeneous. In most cases the Amparihy
Formation is characterised by biotite- and garnet-bearing gneisses. Quartz, K-feldspar and
plagioclase are also present. There is little compositional difference between the Amparihy and
Ihosy Formations, even though these are notable differences in the mineral assemblages from
each formation. The differences reflect the speciation of iron.
The Ihosy Formation rocks are also characterised by a distinctive and well-developed stromatic
migmatitic layering. Cordierite and magnetite are conspicuous in these rocks and are present in
abundances of between 25-50% and 3-10% respectively. These rocks are often garnet absent
Figure 5. Geological Map of Bekisopa Area
10
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
and contain the assemblage cordierite + sillimanite + biotite + plagioclase + K-feldspar + quartz +
ilmenite and magnetite. The rocks have strikes of northwest-southeast and are characterised by
tight to isoclinal folds, mostly showing sub-vertical dips (GAF-BGR, 2008).
The Bekisopa Formation is intercalated with kilometre scale layers of quartzite, impure marbles
(Betainamboa Formation), and quartzo-feldspathic gneisses. These rocks of the Betainamboa
Formation are medium- to coarse-grained and mainly massive, however, weak millimetre to metre
scale compositional banding defined by layers of oxides is also locally present. The rocks have
strikes of northwest-southeast, and are characterised by folds which mostly shows dips to the west
(GAF-BGR, 2009).
The general mapping data is excellent and it can be seen that the Malakialina Formation is the
main host of iron mineralisation in the district, and within the project area is comprised of a
sequence of mica schists, gneiss, marble, quartzite and amphibolite.
A total of 285 diamond drill holes totalling 8,854 have been drilled at the Bekisopa Project from
2020 to 2024 (See Figure 6). Drill spacing for all Indicated resource is 50 by 50m.
Figure 6. Bekisopa site layout, showing magnetic resonance overlaid with drill hole locations
11
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Figure 7. Outcropping of massive magnetite/hematite
The principal lithology seen within the drillcore is gneiss (both mineralised with Fe and barren),plus
schists and calc silicates. Intervals of intense magnetite are present and, in places, become the
overriding rock type.
WAI have developed a geological model to support the PFS. Satellite imagery, ground magnetic
data and drill hole lithology has been used to construct a 3D lithological model across the
Bekisopa tenemental package.
While variable, high levels of oxidation have occurred from surface to 20m in depth, with partial
oxidation occurring below this point to depths of 40m. Iron enrichment is common in the DSO
mineralised zones, creating a high grade regolith profile. levels of oxidation has occurred between
surface and 20 meters depth. Massive magnetite-haematite outcrops along surface (see Figure
7). Magnetite, haematite and small levels of geothite are the principal iron bearing minerals.
12
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Figure 8. Bekisopa Geological Model showing outcrop of massive Magnetite/Hematite
13
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Mineral Resource
The PFS is based on the Bekisopa DSO Mineral Resource Estimate (MRE) detailed in Table 1
below. The Indicated Resource used in the PFS can be summarised as:
•
6.6 Mt at 59.7% Fe Enriched DSO
•
1.8Mt at 39.9% Fe Intermediate A, and
•
0.3 Mt at 33.7% Fe Intermediate B.
The detailed MRE report was released on the ASX on 25/2/2025 (35% Increase in Bekisopa MRE
Total Iron Ore Tonnes).
A cutoff grade of 58% Fe has been used for the enriched DSO in the southern and northern
resource zones, and 50% Fe for the central zone. The small amounts of Intermediate A and B
mineralisation that sit adjacent to the enriched DSO have a cut off grade of 35% Fe and 30% Fe
respectively.
Reference throughout the PFS is also made to the Bekisopa fresh ore zone. This refers to the
previously announced Bekisopa MRE of 194.7 million tonnes at 32% Fe Inferred Resource,
prepared by H&S Consultants Pty Ltd, which encompasses the underlying fresh mineralisation and
is typically referred to as Stage 2.
The detailed MRE report supporting the 194.7 Mt Inferred Resource was released on the ASX on
11 April 2022.
Figure 9. Drill Rig at Bekisopa.
14
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Table 1. Bekisopa 2025 Mineral Resource Estimate
Mineral Resource Estimate for the Bekisopa Project
Free Digging and Rippable Mineral Resources, 7 February, 2025
Tonnes (Kt)
Density (t/m3)
Fe (%)
SiO2 (%)
Al2O3 (%)
P (%)
Indicated
5,724
3.39
60.3
6.1
3.6
0.10
Inferred
902
2.99
55.9
7.7
4.7
0.10
Indicated
1,231
2.38
40.5
23.1
8.2
0.10
Inferred
105
2.33
40.1
23.6
7.4
0.07
Indicated
260
2.54
34.3
29.3
4.9
0.15
Inferred
765
3.41
39.0
24.7
4.6
0.13
Indicated
560
3.19
54.9
11.1
6.1
0.06
Inferred
15
3.07
53.5
12.0
6.4
0.06
Indicated
605
2.65
38.7
23.7
7.4
0.11
Inferred
42
2.65
38.9
23.1
7.6
0.11
Indicated
59
2.75
31.2
2.7
4.2
0.18
Inferred
187
3.2
38.1
17.6
2.6
0.12
Indicated
349
3.11
58.5
7.5
5.46
0.09
Inferred
955
3.49
52.6
11.3
3.4
0.21
Indicated
-
-
-
-
-
-
Inferred
111
2.52
39.3
23.2
5.9
0.13
Classification
Bekisopa South
Enriched DSO
Intermediate A
Intermediate B
Bekisopa Central
Enriched DSO
Intermediate A
Intermediate B
Bekisopa North
Enriched DSO
Intermediate A
Intermediate B
Indicated
Inferred
-
-
-
-
-
-
748
2.71
32.8
23.6
3.7
0.16
Tonnes (Kt)
Density (t/m3)
Fe (%)
SiO2 (%)
Al2O3 (%)
P (%)
Indicated
6,633
3.36
59.7
6.6
3.9
0.10
Inferred
1,872
3.22
54.2
9.6
4.0
0.16
Indicated
1,836
2.46
39.9
23.3
7.9
0.10
Inferred
258
2.46
39.5
23.3
6.8
0.10
Indicated
319
2.57
33.7
29.0
4.7
0.16
Inferred
1700
3.04
36.2
23.4
4.0
0.15
Bekisopa Total
Classification
Enriched DSO
Intermediate A
Intermediate B
15
AKORA RESOURCES
PRE-FEASIBILITY STUDY ON THE BEKISOPA IRON ORE PROJECT
Notes
1. Mineral Resources of the Enriched zones are reported within wireframe boundaries interpreted at nominal cut-off grades of 58%
Fe for Bekisopa South and North and 50% Fe for Bekisopa Central. Mineral Resources of the Intermediate A zones are reported
within wireframe boundaries interpreted at a nominal cut-off grade of 35% Fe. Mineral Resources of the Intermediate B zones
are reported at a cut-off grade of 30% Fe.
2. Mineral Resources are limited by an optimised open pit shell based on appropriate technical and economic parameters.
3.
Mineral Resources are not Ore Reserves until they have demonstrated economic viability based on a Pre-Feasibility Study or
Feasibility Study.
4.
Mineral Resources are reported inclusive of any Ore Reserves.
5.
Mineral Resources have been classified in accordance with the guide