Satrokala drilling returns substantial intercepts of low
grade iron mineralisation.
AKORA Resources Limited (ASX: AKO) (AKORA or Company) has returned substantial
intersections of low-grade iron mineralisation across all five holes at its Satrokala Project in
Madagascar following the receipt of assays from the Company’s recent sighter exploratory drilling
program.
Intercept thicknesses ranged up to 51m and averaged 5.1% Fe (the summary of the drill hole
weighted average iron intercepts is detailed in Appendix 1).
The drill program totalled 501.68m and targeted a 10km long by 2km wide magnetic anomaly
identified in the southern section of the tenement by an initial rock chip sampling and a ground
magnetic survey completed last year1 2. (Refer Figure 1. The confirmed drill hole location and
orientations are shown in Table 1).
AKORA Managing Director and CEO, Mr Paul Bibby said, “the continuous and wide iron
intercepts were extensive and explain the magnetic anomaly but grades were lower than
expected. We will reassess all the Satrokala geological information and determine if there are
areas along the remaining 8km of strike that may contain higher grade magnetite mineralisation
before any future drilling.
“As 2024 draws to a close, we remain squarely focused on our flagship Bekisopa Project. A PreFeasibility Study for a 2 million tonne per annum, high-grade direct shipping ore (DSO) operation
remains on track for completion in early 2025.”
Drillhole ID
URM_x
UTM-y
Inclination
Azimuth
Final depth
SATD01
571,197
7,571,043
SATD02
571,198
7,571,485
-50
66
100.27
-50
246
100.31
SATD03
569,357
7,569,277
-50
76
100.31
SAtD04
SATD05
568,960
7,569,194
-90
0
100.5
569,691
7,569,361
-50
76
100.29
Table 1. Satrokala final drillhole collars summary
1
2
ASX Announcement – High Grade Rock Chips, 8/6/2022
ASX Announcement – Satrokala Magnetic Survey Results, 20/3/2024
1
Figure 1: Map showing magnetic anomalies and drillhole locations at Satrokala.
2
Satrokala assay results
SATD01 drillhole intersected at least five magnetite bearing steeply dipping sections
characterised by fine disseminated magnetite, with quartz/feldspar and dark mafic minerals
probably pyroxene, with biotite and some pyrite and pyrrhotite (magnetic). The iron mineralisation
varied between 2.60m and 28.55m, for a total in thickness of 63.5m, with weighted averages up to
5.69% Fe. The best iron mineralisation intersection includes 4.81m @ 9.3% Fe.
SATD02 drillhole intersected two substantial steeply dipping magnetite sections characterised by
fine disseminated magnetite, with quartz/feldspar and dark mafic minerals probably pyroxene,
biotite and some pyrite and pyrrhotite (magnetic). The iron mineralisation intercepted were 24.3m
and 51.4m, for a total thickness of 75.7m, with weighted averages up to 7.28% Fe.
SATD03 drillhole intersected at least eight steeply dipping magnetite mineralisation sections
characterized by fine disseminated magnetite, with quartz/feldspar and dark mafic minerals
probably pyroxene, biotite and some pyrite and pyrrhotite (magnetic). The iron mineralisation varied
between 3.5m and 15.9m, for a total thickness of 82.8m, with weighted averages up to 8.07% Fe.
SATD04 drillhole intersected at least 10 moderately dipping fine disseminated magnetite sections.
The iron mineralisation sections varied between 0.6m and 20.5m, for a total thickness of 57.9m, with
weighted averages up to 7.9% Fe.
SATD05 drillhole intersected at least seven steeply dipping fine disseminated magnetite sections.
The iron mineralisation units vary between 3.7m and 48.4m, for a total thickness of 89.9m, with
weighted averages up to 8.62% Fe. All drillholes finished in iron mineralisation.
This announcement has been authorised by Akora Resources Limited’s Board of Directors.
For further information please contact:
Paul G Bibby
Managing Director
Phone +61(0) 419 449 833
www.akoravy.com
Gareth Quinn
Investor Relations
Phone +61(0) 417 711 108
gareth@republicpr.com.au
Competent Persons Statements
The information in this statement that relates to Exploration Targets and Exploration Results is based on
information compiled by Mr Jannie Leeuwner – BSc (Hons) Pr.Sci.Nat. MGSSA and is a full-time employee
of Vato Consulting LLC. Mr. Leeuwner is a registered Professional Natural Scientist (Pr.Sci.Nat. 400155/13) with the South African Council for Natural Scientific Professions (SACNASP). Mr. Leeuwner
has sufficient experience which is relevant to the style of mineralisation and type of deposits under
consideration and the activity being undertaken to qualify as a Competent Person as defined in the Note for
Mining Oil & Gas Companies, June 2009, of the London Stock Exchange and the 2012 Edition of the
‘Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code).
Mr. Leeuwner consents to the inclusion of the information in this release in the form and context in which it
appears.
3
Cleaner iron ore for greener steel
AKORA Resources (ASX: AKO) is an Australian resources company focused on the development of four
high-grade iron ore projects in Madagascar.
The Company’s flagship Bekisopa Iron Ore Project has a 194.7 million tonne (mt) Inferred JORC Resource
(ASX Announcement 11 April 2022) with very low impurities able to produce a premium-priced +68% Fe
concentrate. Direct Reduced Iron-Electric Arc Furnace (DRI-EAF) technology which is used to make
greener steel without coal and considerably less carbon emissions requires iron ore grades of at least 67%.
To generate cash in the near-term, AKORA is advancing plans at Bekisopa to produce up to 2Mt per annum
over the first five years of a 60% Fe average grade direct shipping ore (DSO) (ASX Announcement 14
November 2023) for shipping to Blast Furnace-Basic Oxygen Furnace (BF-BOF) steelmakers.
The Company confirms that it is not aware of any new information or data that materially affects the above and that all
material assumptions and technical parameters underpinning the estimates in the relevant market announcement
continue to apply and have not materially changed.
4
Appendix 1: Weighted average summary
Table 2: Satrokala weighted assay results from the 2024 exploration drilling program
Drillhole
ID
SATD01
13.27
To_m Interval_
m
29.24
15.97
31.31
44.00
12.69
3.97
31.31
36.32
5.01
4.67
53.40
57.15
3.75
4.09
58.80
61.40
2.60
3.97
30.16
33.56
3.40
2.28
71.72
100.27
28.55
5.63
33.56
49.50
15.94
2.89
incl.
80.62
85.43
4.81
9.30
incl.
33.56
36.05
2.49
4.69
incl.
91.14
93.02
1.88
9.34
incl.
46.00
47.73
1.73
6.48
SATD02
20.95
45.26
24.31
6.22
51.90
72.38
20.48
1.77
48.95
100.31
51.36
7.28
73.18
83.50
10.32
1.62
incl.
48.95
53.00
4.05
8.17
84.23
85.90
1.67
1.43
SATD03
2.21
11.68
9.47
6.76
86.90
91.36
4.46
2.40
incl.
7.38
9.78
2.40
8.29
93.64
100.50
6.86
1.79
14.70
30.60
15.90
6.63
26.55
29.62
3.07
9.30
33.21
37.00
3.79
8.07
35.68
37.00
1.32
37.97
50.39
37.97
40.69
50.39
incl.
incl.
incl.
incl.
incl.
incl.
incl.
From_m
Fe_pct
5.69
Drillhole
ID
SATD04
incl.
SATD05
From_m
To_m
Fe_pct
3.32
Interval_
m
0.63
2.69
11.56
22.18
10.62
2.76
23.37
30.16
6.79
4.81
23.97
26.21
2.24
5.36
7.91
0.00
5.95
5.95
7.10
5.95
54.38
48.43
8.62
25.05
25.63
0.58
10.12
9.69
55.38
62.29
6.91
7.18
12.42
6.00
62.76
67.47
4.71
5.83
2.72
7.23
68.36
74.00
5.64
6.70
55.56
5.17
3.26
80.55
95.08
14.53
6.01
55.56
71.35
15.79
6.23
85.24
90.45
5.21
8.25
65.35
68.00
2.65
8.08
96.60
100.29
3.69
7.90
74.67
78.13
3.46
5.59
76.60
78.13
1.53
8.99
82.10
85.65
3.55
4.23
87.10
100.31
13.21
4.82
89.68
91.41
1.73
6.91
incl.
incl.
5
Appendix 2: JORC Code, 2012 Edition - Table 1 - Satrokala Project
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
JORC Code explanation
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1
m samples from which 3 kg was pulverised to produce a 30 g charge
for fire assay’). In other cases more explanation may be required,
such as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of detailed information.
Commentary
•
•
•
•
•
•
Drilling
techniques
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
•
Diamond drilling was used to obtain NTW size core, with the
weathered (friable) core split using a chisel/hammer and fresh
(competent) core cut using a diamond blade core saw.
Samples were taken along the depth intervals and lithological
sub-division mark-ups to gather representative samples.
Sampling consists of approx. 1m samples of ½ core with breaks
at lithological discontinuities - typical 1-5kg.
Samples were oven dried, manually crushed to -2mm, split twice
through a 50/50 riffle splitter to obtain a representative subsample of approx. 100g, and then pulverise that >85 % pass -75
μm.
The pulp samples were sent to an accredited laboratory (ALS) in
Perth, Australia for determination of total iron and a standard
“iron suite” of elements by XRF analyses using techniques MEXRF21u for standard iron-ore XRF analysis and method MEGRA05 for LOI analysis.
QA/QC procedures applied with alternating standards and
blanks inserted every 20 samples, and four duplicates (field and
lab) inserted every 100 samples.
Conventional wireline diamond drilling is used to obtain all
drillcore and drilling is undertaken with a EP200 man portable
drilling rig. Nominal core diameter is 56.1mm (NTW) in 0.5-1.5m
runs. Drill holes SATD01, SATD02, SATD03 and SATD05 are
inclined at -50° and SATD04 -90° (vertical) and core is not
orientated. A total of 5 diamond holes (SATD01 to SATD05) and
501.68m drilled.
Criteria
JORC Code explanation
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries
and results assessed.
• Measures taken to maximise sample recovery and ensure
representative nature of the samples.
• Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
• Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
• Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
Logging
Commentary
•
•
•
•
•
•
•
•
•
•
•
Sub-sampling
techniques
and sample
preparation
• If core, whether cut or sawn and whether quarter, half or all core
taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.
•
•
Core recovery is measured every run by geologists.
Core recoveries of 98% on average were achieved for sampled
core.
No bias or relationship has been observed between recovery
and grade.
A set of standard operating procedures for drilling and sampling
were prepared by the company and Vato Consulting, who is
supervising the program, and these are always adhered to.
All drill core is logged qualitatively using standard operating
practices and codes.
Logging included: core recovery %, primary lithology, secondary
lithology, weathering, colour, grain size, texture, mineralisation
type (generally magnetite or hematite), mineralisation style,
estimated mineralisation %, structure, magnetic susceptibility
(see below), notes (longhand).
All core is photographed both wet and dry and as both whole
and half core.
All core is geotechnically logged and RQD’s calculated for every
core run.
All drillholes are logged using a ZH-SM30 magnetic susceptibility
meter to enable accurate distinction of iron (magnetite) rich units
and to potentially differentiate between magnetite and hematite
rich mineralisation. Readings recorded in 25cm intervals.
Density measurements are made using both the Archimedes
method (mainly fresh competent rock) and the Caliper Vernier
(mainly weathered friable rock) methods.
All diamond core holes logged in their entirety.
A set of standard operating procedures for drilling and sampling
were prepared by the company and Vato Consulting, who is
supervising the program, and these are always adhered to.
All core is fitted together so that a consistent half core could be
7
Criteria
JORC Code explanation
• For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
• Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
• Measures taken to ensure that the sampling is representative of the in
situ material collected, including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material
being sampled.
Commentary
•
•
•
Quality of
assay data
and
laboratory
tests
• The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is considered
partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc,
the parameters used in determining the analysis including instrument
make and model, reading times, calibrations factors applied and their
derivation, etc.
• Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels
of accuracy (ie lack of bias) and precision have been established.
•
•
•
•
collected, marked up with a “top” line (line perpendicular to dip
and strike, or main foliation), sample intervals decided and
marked up and the core subsequently cut in half using a core
saw, separating samples into the marked-up intervals. If the
core is weathered (friable), it is split in half using a hammer and
chisel. The intervals are nominally 1m, but smaller intervals are
marked if a change in geology occurred within the 1m interval.
The half core sample intervals are placed into polythene bags
along with a paper sample tag. This is then sealed using a cable
tie and placed into a second polythene bag with a second paper
tag and this is sealed using a cable tie.
Samples are prepared at the OMNIS laboratory in Antananarivo
and samples are oven dried, crushed to -2mm, split twice
through a 50/50 riffle splitter to obtain a representative subsample, weighing approx. 100g and then pulverized that 85%
pass -75µm.
1m sampling is deemed to be comprehensive and representative
for the style/type of mineralisation under investigation.
Pulp samples were sent to ALS an accredited laboratory, in
Perth, West Australia for determination of total iron and a
standard “iron suite” of elements by XRF analyses using
techniques ME-XRF21u for standard iron-ore XRF analysis and
method ME-GRA05 for LOI analysis.
QA/QC inhouse procedures applied with alternating standards
and blanks inserted every 20 samples, and four duplicates (field
and lab) inserted every 100 samples, in addition to the internal
QAQC from the laboratory.
OREAS standards OREAS40 / OREAS401 / OREAS404 /
OREAS701 and AMIS blank AMIS855 were used for inhouse
QAQC.
Standards, blanks, and field and lab duplicates for drill sample
analyses reported in this announcement have performed
8
Criteria
JORC Code explanation
Commentary
satisfactorily.
Verification of
sampling and
assaying
• The verification of significant intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
•
•
•
•
Location of
data points
• Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations
used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
•
•
•
Data spacing
and
distribution
Orientation of
data in
relation to
geological
structure
Sample
security
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and
classifications applied.
• Whether sample compositing has been applied.
• Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering
the deposit type.
• If the relationship between the drilling orientation and the orientation
of key mineralised structures is considered to have introduced a
sampling bias, this should be assessed and reported if material.
• The measures taken to ensure sample security.
•
•
•
•
•
•
All work was completed by Vato Consulting personnel and all
mineralised intervals were checked by Vato Consulting’s
Principal Geologist.
No twin drillholes were drilled.
All data was recorded on paper logs and after captured using
Seequent MXDeposit database software.
No adjustments to assay data were done.
Drillhole collars have been provisionally located using a handheld GPS (+/-2-3m accuracy). Final collar locations will be
completed at the end of the drilling program by using differential
GPS (dGPS) (with an accuracy to cm).
The grid system used is UTM, WGS84, Zone 38 Southern
Hemisphere
No topographical survey has yet been completed.
The drilling lines are broadly perpendicular or slightly oblique to
local geological trends and magnetic units (anomalies).
NA
NA
The drilling lines are broadly perpendicular or slightly oblique to
local geological trends and magnetic units (anomalies).
NA
Chain of Custody procedures are implemented to document the
possession of the samples from collection through to storage,
customs, export, analysis, and reporting of results. Chain of
custody forms are a permanent records of sample handling and
off-site dispatch.
9
Criteria
JORC Code explanation
Commentary
•
•
Audits or
reviews
• The results of any audits or reviews of sampling techniques and data.
•
The on-site Geologist is responsible for the care and security of
the samples from the sample collection to the export stage.
Samples prepared during the day are stored in the preparation
facility in labelled sealed plastic bags.
Samples will be delivered to the preparation laboratory and
subsequent analytical laboratory by courier.
No audit has been conducted.
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
JORC Code explanation
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint
ventures, partnerships, overriding royalties, native title interests,
historical sites, wilderness or national park and environmental
settings.
• The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
Commentary
•
•
•
The Company completed the acquisition of the minority interest
in Iron Ore Corporation of Madagascar sarl held by Cline Mining
Corporation on 5 August 2020.
The Company holds through Iron Ore Corporation of
Madagascar sarl, Universal Exploration Madagascar sarl and
MRM Holdings a total of 13 exploration permits in three
geographically distinct areas. All administration fees due and
payable to the Bureau du Cadastre Minier de Madagascar
(BCMM) have been made and accordingly, all tenements are in
good standing with the government.
The tenements are set out in the below
10
Criteria
JORC Code explanation
Commentary
Project ID
Tenement Holders
Permit ID
Tratramarina
UEM
UEM
UEM
Rakotoarisoa
Rakotoarisoa
16635
16637
17245
18379
18891
Permit
Type
PR
PR
PR
PRE
PRE
MRM
MRM
6595
13011
PR
PR
98
33
MRM
21910
PR
3
IOCM
IOCM
IOCM
IOCM
IOCM
Rafafindravola
10430
26532
35828
27211
35827
3757
PR
PR
PR
PR
PR
PRE
64
768
80
128
32
16
Ambodilafa
Bekisopa &
Satrokala
Number Granting
of Blocks
Date
144
23/09/2005
48
23/09/2005
160
10/11/2005
16
11/01/2006
48
18/11/2005
22/09/2015
23/09/2015
9/11/2015
11/01/2014
17/11/2013
Submission
Date
4/09/2015
4/09/2015
4/09/2015
27/03/2012
27/03/2012
20/05/2003 19/05/2013
15/10/2004 14/10/2014
8/03/2013
7/08/2014
Expiry Date
Actual Status
Under renewal process
Under renewal process
Under renewal process
Under transformation
Under transformation
Under renewal process
Under renewal process
Under substance extension and
23/09/2005 22/09/2015 12/07/2015
renewal process
4/03/2004 3/03/2014 28/11/2013
16/10/2007 3/02/2019
16/10/2007 3/02/2019
16/10/2007 23/01/2017 20/01/2017
23/01/2007 23/01/2017 20/01/2017
26/03/2001 25/11/2019
Under renewal process
Relinquished
Under renewal process
Under renewal process
Under renewal process
Transferred to IOCM Gerant
Exploration
done by other
parties
• Acknowledgment and appraisal of exploration by other parties.
•
In 2007 Spector for Cline Mining Corporation completed ground
geophysical investigations of FUGRO airborne magnetic and
radiometric anomalies. For anomaly Zone F (covering tenements
27211 and 35827) it was concluded to be a very prospective iron
prospect as indicated by a 3 mgal gravity anomaly associated
with a 4500 nT magnetic anomaly. The geophysical features are
quite similar to that observed over Bekisopa and a synformal
structure is interpreted. An east-west geological traverse of
2.0km showed generally flat ground with little outcrop but float
boulders of massive magnetite.
Geology
• Deposit type, geological setting and style of mineralisation.
•
The main lithologies are paragneisses, calc-silicates,
amphibolites/pyroxinites and marbles of Palaeoproterozoic age.
A magnetite-bearing gneiss rock is apparent and this appears to
grade into massive magnetite-hematite layers and lenses. The
mineralisation appears to be a metasomatic alteration product
and has some similarities to skarn style iron mineralisation
and/or magmatic associated IOCG/Kiruna style mineralisation.
Drill hole
Information
• A summary of all information material to the understanding of the
exploration results including a tabulation of the following information
for all Material drill holes:
o easting and northing of the drill hole collar
•
All relevant drillhole information related to the 2024 drilling
program completed to date (SATD01 to SATD05) is included in
this press release and tables.
11
Criteria
JORC Code explanation
•
Data
aggregation
methods
•
•
•
Relationship
between
mineralisation
widths and
intercept
lengths
•
Diagrams
•
Balanced
reporting
Other
substantive
o elevation or RL (Reduced Level – elevation above sea level in
metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from
the understanding of the report, the Competent Person should clearly
explain why this is the case.
In reporting Exploration Results, weighting averaging techniques,
maximum and/or minimum grade truncations (eg cutting of high
grades) and cut-off grades are usually Material and should be stated.
Where aggregate intercepts incorporate short lengths of high grade
results and longer lengths of low grade results, the procedure used
for such aggregation should be stated and some typical examples of
such aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values
should be clearly stated.
These relationships are particularly important in the reporting of
Exploration Results.
If the geometry of the mineralisation with respect to the drill hole
angle is known, its nature should be reported.
If it is not known and only the down hole lengths are reported, there
should be a clear statement to this effect (eg ‘down hole length, true
width not known’).
Appropriate maps and sections (with scales) and tabulations of
intercepts should be included for any significant discovery being
reported These should include, but not be limited to a plan view of
drill hole collar locations and appropriate sectional views.
Commentary
•
Geological interpretations and cross sections of representative
drillholes are presented in this announcement.
•
Significant results reported are weighted averages based upon
sample length and grade.
No cut offs were used as iron is a bulk commodity.
•
•
Drillholes SATD01, SATD02, SATD03 and SATD05 are oblique
to local geological trends and magnetic units (anomalies) and
SATD05 is vertical into geological trends and magnetic units
(anomalies) and the drilling results does not reflect true
thicknesses but the down hole length of the iron mineralisation.
•
All relevant maps and tabulations of drill hole collars and
interpreted cross sections are included in this announcement
that clearly show the relationship of the drilling to the
mineralisation
• Where comprehensive reporting of all Exploration Results is not
practicable, representative reporting of both low and high grades
and/or widths should be practiced to avoid misleading reporting of
Exploration Results.
•
Exploration results reported correspond to the assay results
received for the 5 drillholes (SATD01 to SATD05) drilled to date.
All significant weighted averages results based upon sample
length and grade are reported.
• Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical
survey results; geochemical survey results; bulk samples – size and
•
•
•
•
See results from a surface rock sampling program in 2022 (ASX
Announcement 8 June 2022), and a subsequent follow-up
ground magnetic survey in 2023 (ASX Announcement 20 March
12
Criteria
JORC Code explanation
exploration
data
method of treatment; metallurgical test results; bulk density,
groundwater, geotechnical and rock characteristics; potential
deleterious or contaminating substances.
• The nature and scale of planned further work (eg tests for lateral
extensions or depth extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of possible extensions,
including the main geological interpretations and future drilling areas,
provided this information is not commercially sensitive.
Further work
Commentary
2024), and the Satrokala Iron Ore Project First Exploratory
Drilling – Update (ASX Announcement 15 August 2024).
•
Further mineralogy test work to be completed.
13