31.3.24 Quarterly Activities & Cashflow Report
Released
Released
Announcement PDF
Akora Resources Ltd
ABN 90 139 847 555
ASX Code: AKO
Quarterly Report
31 March 2024
Quarterly
Report
For the quarter ended
31 March 2024
www.akoravy.com.au
AKORA is developing a
high-grade Direct
Shipping Ore (DSO) iron
ore mine in Madagascar.
This will be further
developed into serving
the steel industry’s
accelerating focus on
reducing carbon dioxide
(greenhouse gas)
emissions through
decarbonisation.
Highlights
• A continuous 10km long magnetic anomaly up to 2km
wide has been identified at the Satrokala Iron Ore
Project, confirming the potential of the Company’s
exploration acreage in Madagascar as a substantial
iron ore district.
• There exists the potential to expand the high-grade
Bekisopa Iron Ore Project’s initial 4.4 million tonne
Indicated Direct Shipping Ore (“DSO”) JORC
Resource after 52 out of 65 shallow drill holes
completed in October 2023 across the northern and
central zones intercepted high-grade iron
mineralisation.
• Former BHP Iron Ore President Mr Graeme Hunt
appointed as AKORA’s new Non-Executive Chairman.
• Experienced mining operations and project developer
Mr Jason Whittle appointed as General Manager Development, effective from 15 January 2024.
• Following the release of the Scoping Study, the Board
of Directors resolved to move straight into the PreFeasibility Study.
• AKORA commenced a strategic investor process by
opening access to the Bekisopa Project Data Room.
1|P a g e
Bekisopa Iron Ore Project
Ownership 100% | Madagascar, Africa
The Bekisopa Iron Ore Project in Madagascar hosts an Inferred Resource of 194.7
million tonnes (Mt) with the potential to produce a premium grade 67.6% iron
concentrate suitable for Direct Reduced Iron (DRI) pellets for the steel industry’s
accelerating decarbonisation.
Fourth drill campaign identifies further high-grade direct shipping iron ore at
Bekisopa.
AKORA’s plans to develop a high-grade 61% iron (Fe) average grade direct shipping ore
(DSO) operation at its flagship Bekisopa Project in Madagascar received a boost during the
Quarter after 52 out of 65 drill holes encountered new high-grade iron ore mineralisation.
Assays from this drilling, the Company’s fourth drilling campaign at Bekisopa, completed in
October 2023, returned multiple high-grade iron intersections of DSO style mineralisation at
grades of 58% and above and at depths of between surface to 15m from surface.
The drilling results across Bekisopa’s northern and central zones was designed to increase
the project’s overall DSO Resource tonnage, currently hosted entirely in the project’s
southern zone.
Figure 1: Location of drill holes across Bekisopa’s southern, central and northern zones.
2|P a g e
The assay results will be used by Wardell Armstrong International (WAI) to update the
current Mineral Resource Estimate (“MRE”) for the Bekisopa Project with additional DSO
tonnes expected to add mine life, improve project financials and increase cash flow for our
planned Stage 1 low capital DSO start-up project.
Fourth campaign drilling results
65 shallow drill holes were completed for a total of 905m at a 50 by 50m spacing in the
northern and central zones at Bekisopa. This drilling campaign commenced in July and was
completed in October 2023, and showed an average of 19m of iron mineralisation intercepts
for the northern zone and 12m for the central zone.
Nine additional shallow drill holes were included below outcropping iron ore rock formations
in the southern zone in an area to the east of the 2022 drilling campaign to test for a possible
DSO extension in that area.
Sample of key intercepts (ASX Announcement 11 March 2024):
High grade DSO mineralisation running along the 6-kilometre strike length has been
identified across the exploration area, running at depths from surface to 15m. Assay results
suggest some areas appear to have good consistency of mineralisation.
In line with the interpreted geology of the area, the high-grade DSO zones in the central and
northern zones are not as thick and continuous as the southern zone as the zones become
narrower and more steeply dipping as it progresses north.
Iron mineralisation intercepts in the northern zone averaged around 18.0m, with intercepts of
up to 7.4m and grades of up to 65.4% iron.
Iron mineralisation intercepts in the central zone averaged around 9.2m, with intercepts of up
to 3.6m and grades of up to 65.2% iron.
Iron mineralisation intercepts from the additional drilling at the extension of the southern zone
averaged around 4.3m. Intercepts were returned of up to 5.7m and grades of up to 66.2%
iron.
3|P a g e
Project Overview
The significant scale and particular mineralisation characteristics of Bekisopa’s iron ore
resource presents the Company with several staged development options over time:
1.
Produce 61% Fe average grade direct shipping ore (DSO):
Mine, crush and screen at surface iron ore to produce a 61% Fe average grade lump and
fines product for shipping to Blast Furnace-Basic Oxygen Furnace (BF-BOF) steelmakers.
2.
Produce +62% Fe grade DSO fines
Mine, crush and screen ore to produce a +62% Fe grade fines product for shipping to BFBOF steelmakers.
3.
Produce premium-priced +68% Fe grade concentrate
Using cash generated from Stages 1 and 2, add grinding and magnetic separation circuits
to upgrade ore to a +68% Fe concentrate at 75 microns for shipping to DRI-EAF
steelmakers.
Advancing a high-grade 61% Fe DSO operation at Bekisopa
The Bekisopa iron ore mineralisation has a 6km strike length and comprises the southern,
central and northern zones. In the southern zone, 4.4Mt of Indicated DSO tonnes grading
60.9% Fe have been defined according to JORC standards within the overall total project
Inferred Resource of 194.7Mt.
This DSO Resource formed the basis for the updated Scoping Study announced in
November 2023. The Study found that AKORA could potentially ramp up production to 2
million tonnes per annum (Mtpa) over an initial five-year mine life at Bekisopa. The start-up
operation would produce a 61% Fe average grade lump and fines product for use by Blast
Furnace-Basic Oxygen Furnace (BFBOF) steelmakers and return strong cash flows and
operating cost margin.
The updated Scoping Study shows that the Bekisopa Stage 1 DSO project could build
to 2 million tonnes per year of high-grade Direct Shipping Iron Ore.
In the ’Low CAPEX Case’, an open pit mining operation could produce up to 2Mtpa of DSO,
with the Scoping Study finding that this Bekisopa Stage 1 could deliver an estimated initial
five-year revenue of US$545 million for C1 operating costs of US$45 per wet metric tonne
(wmt) weighted average over initial five years (US$42/wmt at full production rate) and
generate pre-tax operating cash flow of US$270 million.
The estimated upfront capital cost of US$55.3 million1 was based on using contractor labour,
mining equipment (excavators and trucks), mobile processing equipment (crushing and
screening plant) suitable for processing the iron ore into a high-grade 61% Fe average grade
1
The US$55.3M is the “Low CAPEX Case” Contractor Operations / mobile crushing plant capital approach
4|P a g e
lump and fines product. Contractors would also be used for truck hauling the products to port
and for ship loading to keep upfront capital costs contained.
Bekisopa hosts significant potential for growth with only 20% of the project’s 6km strike
length of mineralisation shallow drilled for inclusion in the 2023 Study.
The fourth drilling campaign drillhole results released this Quarter will be included into an
updated Mineral Resource Estimate (MRE), from which it is anticipated that an updated
Scoping Study will be done, including this expanded MRE and anticipated to deliver extra
mine life and improved economics over that stated in the 2023 Scoping Study.
Further, the Study does not include any upside potential DSO tonnes from the Company’s
nearby Satrokala Project where around 30km of prospective strike length of iron ore
mineralisation exists. Exploration success at either Bekisopa and/or Satrokala, both 100%
AKORA owned, would significantly add to this initial five-year DSO Start-Up Plan and result
in significantly improved Study outcomes.
Figure 2. Bekisopa Iron Ore Project location with northern, central and southern zones
delineated. Satrokala Project is located around 20km to the west of Bekisopa.
5|P a g e
Satrokala Project
Ownership 100% | Madagascar
A magnetic survey done in 2023 has
identified a continuous 10km long
magnetic anomaly up to 2km wide..
AKORA’s Satrokala Iron Ore Project has
emerged as a significant prospect after a
recent magnetic survey identified a
major anomaly up to 10km long and 2km
wide, making it some 66% larger than
the Company’s more advanced
Bekisopa Iron Ore Project.
The magnetic survey was completed in
November 2023 and covered just 10km
of prospective iron mineralisation
previously identified in this project area.
Interpretation and results were released
in the reporting period (ASX
Announcement 20 March 2024).
This promising result will assist in
pinpointing exploratory maiden drilling
locations now being planned for in 2024
to confirm iron mineralisation widths,
type and grades.
This is a very significant result,
highlighting that AKORA’s tenement
area is becoming a substantial iron ore
district.”
Satrokala is emerging as a major
component of our exploration and
development strategy and its potential to
deliver high-grade iron ore tonnage will
become clearer as drilling results are
delivered.
The survey was conducted using the
same equipment and approach as
employed at Bekisopa in October 2019.
Three magnetometer units were used
and a team of seven geologists walked
the extent of the tenements under the
supervision of Planetary Geophysics,
Australia.
6|P a g e
Figure 3. The ground magnetic survey area within Satrokala tenements 27211 and 35827.
The Southern area walked on a 25m line spacing, light green area, with the remainder at a
50m line spacing, light blue area.
The magnetic anomalies generated from the survey show the continuous presence of
several magnetic units along the 10km tested. Magnetic responses are in the range of
600nanoTeslas.Three cross sections were modelled to understand the structure and size of
these magnetic units. These cross-sections show the presence of seven to eight northnorthwest/south-southeast striking simple linear units that are steeply dipping, some to an
interpreted depth of +1,000m.
The modelled magnetic units have combined widths at surface of some 450m, in the north
and of some 1,280m in the south with several of the sections of units extending beyond
1,000m in depth.
7|P a g e
Figure 4. AKORA geologist team preparing for the Satrokala magnetic survey and walking
across the tenements and the rich red iron ground.
8|P a g e
Corporate
Cash Position
AKORA Limited held cash reserves at the end of quarter of approximately $0.7 million.
Shareholder Information
As at 31 March 2024, the Company had 643 shareholders and 94,982,814 ordinary fully paid
shares on issue with the top 20 shareholders holding 58.08% of the total issued capital.
ASX Additional Information
ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure spend during the quarter
was $217,913. Full details of exploration activity during the quarter are set out in this report.
ASX Listing Rule 5.3.2: The Company confirms that there was no mine production and
development activities during the quarter.
ASX Listing Rule 5.3.5: Payment to related parties of the Company during the quarter was
$155,049 in cash. A description of and explanation for payments to related parties and their
associates per Section 6.1 of the Appendix 5B following this Quarterly Activities Report is set
out in the table below:
Director Remuneration
Current Quarter
Managing Director fees
117,499
Non-Executive Director fees
35,583
Superannuation
1,967
Total
9|P a g e
155,049
Appointment of Non-Executive Chairman
In January, the Company announced it had appointed former BHP Iron Ore President Mr
Graeme Hunt as Non-Executive Chairman, effective from 1 February 2024.
Mr Hunt started his 34-year career with BHP in the sinter plant at the Port Kembla steel
works, before performing General Management roles covering operations management, port
operations, and corporate strategy. Between 1999 to 2005, he was President BHP Iron Ore
where his global responsibilities spanned the expansion of BHP’s Pilbara operations and the
development of strong commercial relationships with Asian steel mills.
Mr Hunt served as Managing Director (MD) and Chief Executive Officer (CEO) of Lihir Gold
Ltd during which time he managed the company’s takeover by Newcrest Mining for A$9.5
billion.
More recently, he has held MD and CEO positions with both Broadspectrum (formerly
Transfield Services), and Chairman then MD and CEO of AGL Energy Ltd.
Mr Hunt’s commodity experience covers iron ore and steel, coal, manganese, aluminium,
copper, uranium, gold, electricity and gas while his management expertise spans steel
production, exploration, mining, logistics and port operations across Australia, South
America, PNG and West and Southern Africa.
Appointment of General Manager – Development
In January 2024, AKORA appointed mining operations and project developer Mr Jason
Whittle as General Manager - Development, effective from 15 January 2024. Jason has an
Honors degree in Mineral Processing and has worked in operational leadership roles
throughout the mining value chain, in mining and processing, through to marketing, before
progressing to project development and implementation roles on major projects across
Australia, Peru and Africa, working for Pasminco, Zinifex, OZ Minerals and MMG. Jason was
most recently General Manager – Projects at Podium Minerals covering resource
development, study management with internal and external resources, metallurgical
testwork, financial modelling, environmental and license planning and ESG.
Strategic Investor Process
In February, the Company announced that following the release of its Scoping Study there
had been requests for further information on AKORA’s Bekisopa Iron Ore Project.
Subsequently, the Company has opened an online Data Room for a Strategic Investor
Process. Selected parties have already been provided access to the Data Room and the
company is in discussion with other potential strategic investors. Two non-binding indicative
finance offers have been received as at time of reporting; these are being analysed.
Board and Senior Management
Graeme Hunt
Paul Bibby
Matthew Gill
Shane Turner
Jason Whittle
10 | P a g e
Non-executive Chairman
Managing Director & Chief Executive Officer
Non-executive Director
Chief Financial Officer & Company Secretary
General Manager - Development
Trading Halt
Subsequent to the end of the quarter, the securities of AKORA were placed in trading halt at
the request of AKORA on 15 April 2024. Normal trading resumed on 17 April 2024 when the
Company announced a Capital Raising of approximately $3.8 million. It had received firm
commitments for a Placement of new shares at $0.15 per share to raise gross proceeds of
approximately $0.8 million (before costs) to be followed by a 1 for 5 pro-rata nonrenounceable Entitlement Offer at $0.15 per share to raise gross proceeds of approximately
$3 million. Funds will be used to advance development of the Bekisopa and Satrokala
projects in Madagascar and provide for working capital and costs of the Capital Raising.
ASX Announcements during the quarter
The following announcements were lodged on the ASX Market Announcements Platform
during the quarter:
Date
Description
22 March 2024
20 March 2024
11 March 2024
7 March 2024
21 February 2024
30 January 2024
17 January 2024
Annual Report to shareholders
10km Magnetic Strike at Satrokala Iron Ore Project
Drilling Identifies Further High Grade Iron Ore Revised
Drilling Identifies Further High Grade Iron Ore
Strategic Investor Process
Former BHP Iron Ore President Grame Hunt Appointed Chairman
Appointment of General Manager - Development
These announcements are available for viewing on the Company’s website
www.AKORAvy.com.
Other details
Head Office
12 Anderson Street West
Ballarat Vic 3350
Phone: +61 419 449 833
Website: www.AKORAvy.com
This announcement is authorised by the Board.
For further information contact:
Paul Bibby
Managing Director
AKORA Resources
+ 61 (0) 419 449 833
paul.bibby@AKORAvy.com
11 | P a g e
Matthew Lindh
Corporate Advisor
Harbury Advisory Pty Ltd
+ 61 (0) 432 363 933
mlindh@harbury.com.au
Gareth Quinn
Investor Relations
Republic PR
+ 61 (0) 417711108
gareth@republicpr.com.au
Competent Persons’ Statement
The information in this statement that relates to Exploration Targets and Exploration Results
is based on information compiled by Mr Jannie Leeuwner – BSc (Hons) Pr.Sci.Nat. MGSSA
and is a full-time employee of Vato Consulting LLC. Mr. Leeuwner is a registered
Professional Natural Scientist (Pr.Sci.Nat. - 400155/13) with the South African Council for
Natural Scientific Professions (SACNASP). Mr. Leeuwner has sufficient experience which is
relevant to the style of mineralisation and type of deposits under consideration and the
activity being undertaken to qualify as a Competent Person as defined in the Note for Mining
Oil & Gas Companies, June 2009, of the London Stock Exchange and the 2012 Edition of
the ‘Australian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’ (JORC Code). Mr. Leeuwner consents to the inclusion of the information in this
release in the form and context in which it appears.
The information in this report that relates to Mineral Processing and related scientific and
technical information, is based on, and fairly represents information compiled by Mr Paul
Bibby. Mr Bibby is a Metallurgist and Managing Director of AKORA Resources Limited
(AKO), as such he is a shareholder in AKORA Resources Limited. Mr Bibby is a Fellow of
the Australasian Institute of Mining and Metallurgy (FAusIMM). Mr Bibby has sufficient
experience which is relevant to the styles of mineralisation and its processing under
consideration and to the activity which he is undertaking to qualify as a Competent Person as
defined in the JORC Code. Mr Bibby consents to the inclusion in this report of the matters
based on his information in the form and context in which it appears including analytical, test
data and mineral processing results.
The information in this report that relates to Mineral Resources for the South Bekisopa Iron
Project as announced on the 10thJuly 2023 is based on information prepared by Mr Richard
Ellis BSc, MSc, MCSM, FGS, CGeol, EurGeol and is a full-time employee of Wardell
Armstrong International. Mr Ellis is a Chartered Geologist of the Geological Society of
London and has sufficient experience relevant to the style of mineralisation, the type of
deposit under consideration and to the activity undertaken to qualify as a Competent Person
as defined in the 2012 edition of the ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves’. Mr Ellis consents to the inclusion of the information in
the release in the form and context in which they appear.
12 | P a g e
Tenement Interests
As at 31 March 2024, the Company had interests in the following tenements (as required by
Listing Rule 5.3.3). There were no changes in the Company’s interests in tenements during
the quarter.
Project
Location
Tenement Number
Blocks
Bekisopa PR
Madagascar, Africa
10430
64
100%
Bekisopa PR
Madagascar, Africa
27211
128
100%
Bekisopa PR
Madagascar, Africa
35827
32
100%
Bekisopa PRE
Madagascar, Africa
3757
16
100%
Samelahy PR
Madagascar, Africa
6595
98
100%
Samelahy PR
Madagascar, Africa
13011
33
100%
Samelahy PR
Madagascar, Africa
21910
3
100%
Madagascar, Africa
16635
144
100%
Madagascar, Africa
16637
48
100%
Madagascar, Africa
17245
160
100%
Madagascar, Africa
18379
16
100%
Madagascar, Africa
18891
48
100%
Tratramarina East
PR
Tratramarina East
PR
Tratramarina East
PR
Tratramarina West
PRE
Tratramarina West
PRE
13 | P a g e
Current Interest
Mineral Resources and Ore
Reserves
AKORA’s Resource at 31 March 2024
Southern Zone
TOTAL DSO
Indicated
Inferred
4.42
1.12
60.86
58.34
SiO2 (%)
7.01
6.37
4.80
6.04
5.61
6.14
TOTAL DSO
Indicated and Inferred
5.54
60.35
5.72
Western DSO Zone
Eastern DSO Zone
Classification
Indicated
Inferred
Indicated
Inferred
Tonnes (Mt)
1.63
0.33
2.80
0.79
Fe (%)
60.15
58.83
61.28
58.13
Al2O3 (%)
2.65
2.54
3.38
4.23
Density (t/m3)
3.68
3.74
3.21
2.92
3.11
3.73
3.37
3.13
3.24
3.32
Table 1.
Upgraded Bekisopa Southern Zone DSO Resource, ASX Announcement 11 July 2023.
14 | P a g e
Company Profile
Cleaner iron ore for greener steel
AKORA Resources (ASX: AKO) is an Australian resources company focused on the
development of four high-grade iron ore projects in Madagascar.
The Company’s flagship Bekisopa Iron Ore Project has a 194.7 million tonne Inferred JORC
Resource with very low impurities able to produce a premium-priced +68% Fe concentrate.
Direct Reduced Iron-Electric Arc Furnace (DRI-EAF) technology which is used to make
greener steel without coal and considerably less carbon emissions requires iron ore grades
of at least 67%.
To generate cash in the near-term, AKORA is advancing plans at Bekisopa to produce up to
2Mt per annum over the first five years of a high-grade 61% Fe average grade direct
shipping ore (DSO) for shipping to Blast Furnace-Basic Oxygen Furnace (BF-BOF)
steelmakers.
15 | P a g e
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
AKORA Resources Limited
ABN
Quarter ended (“current quarter”)
90 139 847 555
31 March 2024
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
1.2
Receipts from customers
Payments for
(a) exploration & evaluation
(b) development
(c) production
(d) staff costs
(e) administration and corporate costs
Dividends received (see note 3)
Interest received
Interest and other costs of finance paid
Income taxes paid
Government grants and tax incentives
Other
(Cash Boost from Commonwealth
Government)
Net cash from / (used in) operating
activities
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
(e) investments
(f) other non-current assets
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
Cash flows from loans to other entities
Dividends received (see note 3)
2.2
2.3
2.4
16 | P a g e
Year to date
(3-months)
$A’000
-
-
(193)
(197)
(193)
(197)
3
3
(387)
(387)
(218)
(218)
Consolidated statement of cash flows
2.5
2.6
Other
Net cash from / (used in) investing
activities
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
Proceeds from issue of convertible debt
securities
Proceeds from exercise of options
Transaction costs related to issues of equity
securities or convertible debt securities
Proceeds from borrowings
Repayment of borrowings
Transaction costs related to loans and
borrowings
Dividends paid
Other (provide details if material)
Net cash from / (used in) financing
activities
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
Net cash from / (used in) operating
activities (item 1.9 above)
Net cash from / (used in) investing activities
(item 2.6 above)
Net cash from / (used in) financing activities
(item 3.10 above)
Effect of movement in exchange rates on
cash held
Cash and cash equivalents at end of
period
4.2
4.3
4.4
4.5
4.6
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Year to date
(3-months)
$A’000
(218)
(218)
-
-
1,314
1,314
(387)
(387)
(218)
(218)
-
-
2
2
711
711
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in
the consolidated statement of cash
flows) to the related items in the
accounts
5.1
5.2
5.3
5.4
5.5
Bank balances
Call deposits
Bank overdrafts
Other US dollar accounts
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
17 | P a g e
17
631
19
1,200
63
711
95
1,314
6.
Payments to related parties of the entity and their
associates
6.1
6.2
Current quarter
$A'000
Aggregate amount of payments to related parties and their
associates included in item 1
Aggregate amount of payments to related parties and their
associates included in item 2
155
-
Note: Salaries and superannuation for directors.
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
7.
Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
Add notes as necessary for an understanding of
the sources of finance available to the entity.
7.1
7.2
7.3
7.4
Loan facilities
Credit standby arrangements
Other (Convertible Notes)
Total financing facilities
7.5
7.6
Unused financing facilities available at quarter end
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
$A’000
8.
Estimated cash available for future operating activities
8.1
8.2
8.3
8.4
8.5
8.6
8.7
Net cash from / (used in) operating activities (item 1.9)
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
Total relevant outgoings (item 8.1 + item 8.2)
Cash and cash equivalents at quarter end (item 4.6)
Unused finance facilities available at quarter end (item 7.5)
Total available funding (item 8.4 + item 8.5)
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
(387)
(218)
(605)
711
711
1.18
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A.”
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
18 | P a g e
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating cash
flows for the time being and, if not, why not?
Answer: Placement completed 24/04/24 for $0.8 million and Entitlement Offer opened
30/4/24 for $3 million.
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further cash to
fund its operations and, if so, what are those steps and how likely does it believe that they
will be successful?
Answer: Refer 8.8.1
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Yes. Refer 8.8.1
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
19 | P a g e
Compliance statement
1
2
This statement has been prepared in accordance with accounting standards and policies which comply with Listing
Rule 19.11A.
This statement gives a true and fair view of the matters disclosed.
Date:
30 April 2024
Authorised by:
Board of directors
(Name of body or officer authorising release – see note 4)
Notes
1.
2.
3.
4.
5.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s activities for the
past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose additional information
over and above the minimum required under the Listing Rules is encouraged to do so.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB
6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly cash flow report
has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent
standards apply to this report.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the
accounting policy of the entity.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board.” If it has been authorised
for release to the market by a committee of your board of directors, you can insert here: “By the [name of board committee – e.g. Audit and Risk
Committee].” If it has been authorised for release to the market by a disclosure committee, you can insert here: “By the Disclosure Committee.”
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying with
recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and Recommendations, the board should have
received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been properly maintained, that this
report complies with the appropriate accounting standards and gives a true and fair view of the cash flows of the entity, and that their opinion has
been formed on the basis of a sound system of risk management and intern