Project Update - Bekisopa and Satrokala Activities
Released
Released
Announcement PDF
Akora Resources Limited
PO Box 28
Ballarat Victoria 3350
Australia
info@akoravy.com
ACN 139 847 555
ASX: AKO
akoravy.com
18 June 2024
ASX RELEASE
Project Update – Bekisopa and Satrokala activities.
Highlights
•
AKORA has completed an infill drilling program at its advanced Bekisopa high-grade Iron
Ore Project in Madagascar.
•
Technical (geotechnical and hydrological) drilling at Bekisopa is planned to commence in
the coming fortnight to support the Pre-Feasibility Study that is well underway.
•
Satrokala environmental permit for early exploration works approved.
•
Satrokala maiden exploration drilling program planned and prepared for July.
•
Strategic Investor process continues with an in-country visit having been hosted in May.
AKORA Resources (ASX: AKO) (“AKORA” or “Company”) continues to make strong progress at its
flagship Bekisopa high-grade Iron Ore Project, with a 500m infill drilling now completed across 64
shallow holes.
Close on the heels of the Company announcing a major Mineral Resource Estimate (MRE)2 upgrade
at Bekisopa, the campaign comprised holes of between 5m and 20m deep which have targeted the
shallow, weathered Direct Shipping Ore (DSO) material.
Supported by a recent A$3.8 million capital raising1, AKORA is progressing a Pre-Feasibility Study
(PFS) for a start-up Stage 1 DSO operation at Bekisopa which will produce up to 2 million tonnes per
annum (Mtpa) of a high-grade +60% Fe average grade lump and fines product for use by
Steelmakers.
AKORA General Manager Development, Jason Whittle said “visiting Madagascar and the project
sites with a prospective Strategic Investor in May has helped crystalise the necessary actions and
priorities for AKORA to continue developing the Bekisopa PFS. Meeting key in-country government
officials, community leaders, service providers was instrumental. Committing to the next stages of
exploration and technical drilling and preparing for the detailed environmental and social assessment
will all help advance the project towards commercialisation.”
“Visiting the Satrokala Project site, with its 10km long magnetic anomaly, was a highlight of the visit.
With an environmental permit for early exploration works approved at the project, I am very excited to
have committed to the maiden exploration drill program which will get started in July.”
1 Refer ASX Announcement dated 22 May 2024
Bekisopa Site Drilling
The infill holes focused on the southern resource zone and were sited according to drilling completed
in October last year and the results of the MRE update2. The hole spacings were set at 50 by 50m
intervals to best allow any identified resource material to move from inferred to indicated status. The
western most drill holes are hoped to provide some step out information for the resource planning
and could potentially increase the resource area and further define the geological features of the iron
ore on the western extremity. The infill drilling was completed in June safely, on time and on Budget.
Figure 1. Bekisopa Planned Infill Drilling Locations 2024 (Southern Resource Zone) [orange dots]
Further to the infill drilling program, geotechnical and hydrogeological drilling programs are also
planned at Bekisopa for June and July to support the project’s PFS, which is being completed by
Wardell Armstrong International (WAI).
Geotechnical drilling will focus on providing required rock and geological structural properties to
allow for the mining and geotechnical design of the DSO open pits. The campaign will be
conducted in all three resource areas, being North, Central and the dominant Southern resource
zones (see plan view of the resource areas in Figure 2).
The hydrological drill rig will be drilling deep water monitoring holes in the north and southern
resource areas to provide important information on the presence of sub-surface water which will
be used to inform the mine design and environmental management plans developed through the
PFS. Shallow water monitoring bores will also be installed allowing AKORA to accumulate long
term base line water information which will be crucual in planing for future operations.
These drilling programs are being conducted by experienced in-country providers and are being
supported by AKORA, the Company’s in-country team and the engineering leads from WAI.
2 Refer ASX Announcement 3 June 2024
2
Figure 2. Bekisopa Resource Zone Overview (Showing drilling locations up to 2023)
Satrokala Maiden Exploration Drilling
The nearby Satrokala iron ore Project, for which AKORA recently released the ground magnetic
survey findings3 (see Figure 3 overleaf), has received its exploration environmental permits from the
Mining Ministry of Madagascar.
Plans are now in place to commence the maiden drill exploration program on the Satrokala Project
site. A 1,000m drill program has been planned and is expected to commence in July, providing the
first drill hole results for this prospective region. The ground magnetic survey results and the surface
rock chip sampling information4 have been used to inform the planned drill hole locations. An initial
10 holes are planned to a depth of 100m each.
Assay results are scheduled for October 2024 to take account of drilling completion, transport and
logistics and then assaying timelines.
3 Refer ASX Announcement 20 March 2024.
4 Refer ASX Announcement 08 June 2022.
3
Figure 3. Satrokala Ground Magnetic Survey Image
4
Strategic Investor Process
AKORA is pleased to continue to advise the market on its Strategic Investor Process as
previously communicated in the Company’s announcements in February and April 20245,6. The
Strategic Investor Process involves multiple parties, whereby AKORA is seeking the most
suitable funding partner for the development of AKORA’s iron ore Projects.
AKORA is actively working on two Non Binding Indicative Offer (NBIO) submissions, while
continuing to field interest from other parties in potentially providing new submissions. One party
has conducted site visits to the Bekisopa and Satrokala Project locations in May (see Figure 4
below).
There remains a variety of funding structures and valuations being proposed of which the Board
is continuing to carefully consider and work through these options. The Board remains
encouraged by the proposals and discussions held to date.
Figure 4. Strategic Investor Visit Bekisopa Project May 2024
-------------------------------------------------------------5 Refer ASX Announcement 21 February 2024.
6 Refer ASX Announcement 17 April 2024.
5
This announcement has been authorised by Akora Resources Limited’s Board of
Directors.
For further information please contact:
Paul G Bibby
Managing Director
Phone +61(0) 419 449 833
www.akoravy.com
Gareth Quinn
Investor Relations
Phone +61(0) 417 711 108
gareth@republicpr.com.au
Competent Persons Statements
The information in this statement that relates to Exploration Targets and Exploration Results is based on
information compiled by Mr Jannie Leeuwner – BSc (Hons) Pr.Sci.Nat. MGSSA and is a full-time employee
of Vato Consulting LLC. Mr. Leeuwner is a registered Professional Natural Scientist (Pr.Sci.Nat. - 400155/13)
with the South African Council for Natural Scientific Professions (SACNASP). Mr. Leeuwner has sufficient
experience which is relevant to the style of mineralisation and type of deposits under consideration and the
activity being undertaken to qualify as a Competent Person as defined in the Note for Mining Oil & Gas
Companies, June 2009, of the London Stock Exchange and the 2012 Edition of the ‘Australian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code). Mr. Leeuwner
consents to the inclusion of the information in this release in the form and context in which it appears. The
information in this document that relates to the Mineral Resource estimate of the Bekisopa project is based
on, and fairly represents information and supporting documentation compiled and reviewed by Mr. Richard
Ellis, a full-time employee of Wardell Armstrong International and independent of Akora Resources. Mr. Ellis
is a Chartered Geologist (CGeol) and Fellow of the Geological Society of London, and European Geologist
(EurGeol) of the European Federation of Geologists, and has sufficient experience which is relevant to the
style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to
qualify as a Competent Person as defined in the December 2012 edition of the "Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves" ('JORC Code'). Mr. Ellis consents
to the inclusion in the report of the matters based upon the information in the form and context in which it
appears.
6
Iron ore for tomorrow’s steel making
AKORA Resources (ASX: AKO) is an Australian resources company focused on the development
of four high-grade iron ore projects in Madagascar.
The Company’s flagship Bekisopa Iron Ore Project has a 194.7 million tonne (mt) Inferred JORC
Resource with very low impurities able to produce a premium-priced +68% Fe concentrate. Direct
Reduced Iron-Electric Arc Furnace (DRI-EAF) technology which is used to make greener steel
without coal and considerably less carbon emissions requires iron ore grades of at least 67%.
To generate cash in the near-term, AKORA is advancing plans at Bekisopa to produce up to 2Mt
per annum over the first five years of a 60% Fe average grade direct shipping ore (DSO) for
shipping to Blast Furnace-Basic Oxygen Furnace (BF-BOF) steelmakers.