December 2022 Quarterly
Released
Released
Announcement PDF
Quarterly
Activities Report
For the period ending
31 December 2022
31 December 2022
Quarterly Report
Highlights
- Completed infill drilling programme to enhance the DSO resource with
core samples transferred to Perth for final assays
- Completion of scoping study with Wardell Armstrong International
(WAI) confirming the potential for a two-phased development strategy
with the first phase being a robust DSO project and the second phase
as either iron ore fines or very high-grade iron concentrate project
Pursuant to the requirements of the Listing Rules, the Board of Directors for AKORA Resources Limited
has approved this announcement on the Quarterly Activities Report and Quarterly Cashflow Report.
For more information:
Paul Bibby
Managing Director
Akora Resources
+ 61 (0) 419 449 833
paul.bibby@akoravy.com
2|Page
Peter Taylor
Media & Investor Relations
NWR Communications
+ 61 (0) 412 036 231
peter@nwrcommunications.com.au
31 December 2022
Quarterly Report
AKORA Resources Limited (the Company) is pleased to report its activities during the
December 2022 quarter.
Completion of DSO in-fill drilling campaign
On 18 October 2022 AKORA successfully completed the 2022 Bekisopa Southern Zone Direct Ship Ore (DSO) in-fill drilling campaign on tenement PR 10430 with drilling having commenced on 8 September 2022.
A total of 1,165.4 metres drilled across 85 holes at an average depth of 13.7 metres and an
excellent 94% drill core recovery.
The location of the in-fill drill holes was determined with reference to the DSO assays from
the 2020-2021 drilling programmes with further targets in the near-surface eastern and western areas in the Southern Zone. It is in these areas where previous drilling intercepted highgrade iron mineralization, see Figure 1.
The in-fill drilling programme was conducted on a 50-metre by 50-metre grid, designed to upgrade the Mineral Resource Estimate from Inferred Resources to Measured & Indicated Resources. Drill hole depth ranged from 5.6 metres to 29.6 metres, averaging 13.7 metres. The
metres drilled were greater by 315 metres than originally planned, due to iron mineralisation
intercepted being higher than expected per drill hole. The efficient execution of the drilling
programme enabled the Company to add three additional drill holes within the approved
budget.
Figure 1
The in-fill drilling grid on the eastern and western areas of the Southern Zone.
The drilling comprises 85 drill holes for 1,165 meters.
Encouraging iron mineralisation intercepts from surface were observed and believed suitable
for DSO lump and fines iron ore products, see Figures 2 (a) and (b).
3|Page
31 December 2022
Quarterly Report
(a)
(b)
Figure 2
Drill core from in-fill drill holes 106 (a) and 121 (b) showing high-grade iron mineralisation
as determined by magnetic susceptibility reading of >1000.
These drill core iron mineralisation intercepts indicate depths of
~14 metres and ~10 metres, respectively.
The drilling programme was completed within 41 days due to the excellent performance of
the drilling contractor, CDS, and geological consultants, VATO, with great assistance from
community workers from the nearby Bekisopa and Tanamarina villages.
Figure 3 shows the drill rig and the black drilling fluid indicating high-grade magnetite.
(a)
(b)
Figure 3
The drill rig in operation at in-fill drill hole 116.
Generally, the drilling fluids are a reddish colour like the surrounding ground and
occasionally the drilling fluid turns black, arrow in Figure 3(a),
indicating a very high-grade magnetite intercept.
Corresponding drill core, Figure 3 (b), from 3.8 metres to 4.8 metres, arrow in Figure 3(b),
showing a black mineralisation compared to the typical red iron at 0 to 2.6 metres.
Magnetic susceptibility reading was >1000, indicating high-grade iron.
4|Page
31 December 2022
Quarterly Report
It is important for shareholders to note, the in-fill drilling programme was conducted on only
one-fifth of the strike length in the Southern Zone and accordingly, the Company believes
there is potential to increase the DSO tonnage with further drilling programmes.
Government visits to the project area
During the drilling programme, AKORA management met with two groups of visitors. The
first group of visitors being six employees from the Ministry of Mines based in Antananarivo
and Fianaransoa. This was the second visit by the Ministry of Mines to the project area with
representatives impressed with the progress of the Bekisopa project and the active participation of the community in the exploration programme. The second group of visitors were
largely from the Fianaransoa District gendarmerie responsible for overseeing policing around
the Bekisopa area.
Both visiting groups viewed the exploration activities of the Company extremely favourably
and looked forward to further advancement of the Bekisopa project in the region.
Figure 4.
Visitors from the Mining Ministry at Bekisopa on 5 October.
The six people on the right are from the Ministry of Mines located in Antananarivo and Fianaransoa
The Company inspected the OMNIS Mineral Processing Laboratory in Antananarivo as part
of its continuous review of in-country facilities. The OMNIS laboratory is well equipped and
conducts its activities in accordance with the quality assurance and quality controls policies
and procedures set out by the Company.
The assay pulps prepared by OMNIS are transported to Western Australia for analysis at the
ALS facilities in Perth.
Figure 5 shows various stages of sample preparation of the drill core material from Bekisopa.
The black and dark red colour ground material is typically higher-grade iron and the lighter
colour samples being lower iron grade or the country rock intercepted below the iron mineralisation.
5|Page
31 December 2022
Quarterly Report
(a)
(b)
(c)
Figure 5
Bekisopa DSO in-fill drill core samples at various stages of preparation at the
OMNIS Laboratory in Antananarivo.
Drill core samples as received from site (a), dried and crushed samples to be ground (b)
and freshly ground sample (c).
ALS final assays
The first 914 assay pulps, out of a proposed total of 1,262 assay pulps, have been delivered
to the ALS Iron Ore Technical Centre in Perth. The Company will update the market progressively as assays are received.
The Company expects that these iron assays will better define the DSO tonnage and grade
across the Southern Zone and enable the quantification of a higher quality DSO Mineral Resource calculation.
The DSO drill assays from the 2020-2022 drilling programmes, in combination with a selective mining and processing methodology, have the potential for the Company to develop a
five or six years of high-grade DSO low capital/operating cost mining operation. The DSO
will provide the basis for future production of either high-grade iron ore fines, suitable for sintering, or a very high-grade iron concentrate of +68%Fe suitable for Direct Reduction Iron
pellets necessary for Green Steel production.
Completion of scoping study for Bekisopa DSO, fines and concentrate options
Wardell Armstrong International Limited (WAI) completed a Scoping Study for the Bekisopa
Iron Ore project in November 2022. The study findings were very encouraging; however, the
details within the scoping study were unable to be disclosed due to the Bekisopa Mineral Resource Estimate (MRE) of 194.7 million tonne being classified as only an Inferred Resource.
WAI developed three project scenarios:
Scenario 1
DSO mining and processing of known DSO mineralisation within the Inferred Mineral Resource (ASX Announcements 23 March and 11 April
2022).
This scenario is the starting phase for each of the other two scenarios:
Scenario 2
6|Page
DSO production, as described in Scenario 1, followed by the mining and
production of a high-grade crushed 2 mm fines product.
31 December 2022
Quarterly Report
Scenario 3
DSO production, as described in Scenario 1, followed by mining and production of a premium grade concentrate at 75 microns.
WAI considers the Bekisopa project to have significant potential due to its high grades, low
impurities, and positive processing characteristics. The Scoping Study demonstrates the potential of the Bekisopa project with the board of directors agreeing that the next phase of
work being a Pre-feasibility Study for the DSO phase (Scenario 1).
The PFS will be commenced once the DSO MRE is updated with the results from the DSO
in-fill drilling assays expected to define the DSO tonnage and grade with the MRE classification to be Measured & Indicated Resources.
The final assays are expected in April 2023.
It is also important to note that WAI concluded that the exploration of the Satrokala tenement
should be fast-tracked, as this area has potential to be a Bekisopa “look-alike” that is closer
to existing infrastructure.
ASX Listing Rule 5.3.4
The Company expended $0.815 million during the quarter.
Pursuant to Listing Rule 5.3.4 the Company wishes to inform shareholders that expenditure
undertaken for the 24-month period since the listing of the Company on the ASX has been in
accordance with the prospectus. The additional funds raised by the Company from the
exercise of options and an equity raising in 2022 has been expended on its projects and
specifically, accelerating work programmes at the Bekisopa project.
AKORA RESOURCES LIMITED
Sources and Uses of Funds
Prospectus
Cash balance at start of period
Sources of funds
Proceeds from equity raisings
Capital raise
Costs of equity raisings IPO and capital raise)
Exercise of options
Funds available
Uses of funds
Exploration (direct and indirect)
Tenement fees
Corporate costs
Exchange fluctuation
Working capital
Actual
Sources/Uses
1,203,000
1,407,820
5,000,000
5,000,000
3,218,000
-854,027
623,621
7,987,594
9,395,414
-566,000
4,434,000
5,637,000
-3,745,000
-240,000
-762,000
-4,747,000
890,000
-6,031,791
-186,405
-2,286,232
-169,220
-8,673,648
721,766
Notes
Actual opening cash balance exceeded prospectus estimate due to timing-related settlement of corporate costs
Actual sources and uses reflect funds from 1 October 2020 (the date of the preparation of the sources and uses)
Corporate costs includes outstanding costs as at 1 October 2020 settled in November and December 2020
7|Page
31 December 2022
Quarterly Report
Working capital
On 4 April 2022, the Company informed the market that it had completed a Capital Raise
earlier than expected under the prospectus. The decision to raise additional equity resulted
from the acceleration of the 2022 exploration programme. In total, the Company has $0.7
million in available funds at the end of the quarter, 31 December 2022, which are sufficient to
conduct its business for Quarter 2 of 2023.
Capital structure
Capital structure as at XX January 2023 is as follows:
Fully paid ordinary shares (tradeable)
72,190,210
----------------
Options over ordinary shares
Tranche A (45 cents) vest 17 May 2023
Tranche B (55 cents) vest 17 May 2024
Tranche C (65 cents) vest 17 May 2025
650,000
650,000
650,000
During the quarter, outstanding options over ordinary shares granted to investors (7,905,268
options) and brokers (2,244,750 options) pursuant to the listing of the Company expired outof-the-money.
Related parties
During quarter no related party acquired shares in the Company.
Shares previously subject to a compulsory escrow under the ASX Listing Rules were
released on 16 December 2022 and accordingly, shares held by the directors and their
related parties were released from escrow.
ASX Listing Rule 4.10.19
In accordance with Listing Rule 4.10.19, the board of directors wish to confirm that the Group
has been utilising the cash and assets in a form readily convertible to cash that it held at the
time of its admission to the Official List of ASX on 15 December 2020 and since its admission
to the end of the reporting period (being 31 December 2022) in a way that is consistent with
its business objectives.
Board of directors
MH Stirzaker
PG Bibby
JM Madden
Non-executive Chairman
Managing Director and Chief Executive Officer
Executive Director and Company Secretary
Website
www.akoravy.com
8|Page
31 December 2022
Quarterly Report
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
AKORA Resources Limited
ABN
90 139 847 555
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
1.2
Receipts from customers
Payments for
(a) exploration & evaluation
(b) development
(c) production
(d) staff costs
(e) administration and corporate costs
Dividends received (see note 3)
Interest received
Interest and other costs of finance paid
Income taxes paid
Government grants and tax incentives
Other
(Cash Boost from Commonwealth Government)
Net cash from / (used in) operating activities
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
(e) investments
(f) other non-current assets
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
Cash flows from loans to other entities
Dividends received (see note 3)
Other
Net cash from / (used in) investing activities
2.2
2.3
2.4
2.5
2.6
9|Page
Quarter ended (“current quarter”)
31 December 2022
Current quarter
$A’000
Year to date
(twelve months)
$A’000
-
-
(633)
(2,204)
(34)
(148)
(516)
(873)
(815)
(3,593)
-
-
31 December 2022
Quarterly Report
Consolidated statement of cash flows
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
Proceeds from issue of convertible debt securities
Proceeds from exercise of options
Transaction costs related to issues of equity
securities or convertible debt securities
Proceeds from borrowings
Repayment of borrowings
Transaction costs related to loans and borrowings
Dividends paid
Other (provide details if material)
Net cash from / (used in) financing activities
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
Current quarter
$A’000
Year to date
(twelve months)
$A’000
3,221
206
(157)
-
3,270
4.
Net increase / (decrease) in cash and
cash equivalents for the period
(815)
(323)
4.1
Cash and cash equivalents at beginning of
period
Net cash from / (used in) operating activities (item 1.9 above)
Net cash from / (used in) investing activities
(item 2.6 above)
Net cash from / (used in) financing activities
(item 3.10 above)
Effect of movement in exchange rates on
cash held
Cash and cash equivalents at end of period
1,537
1,045
(815)
(3,593)
-
-
-
3,270
-
-
722
722
4.2
4.3
4.4
4.5
4.6
5.
5.1
5.2
5.3
5.4
5.5
Reconciliation of cash and cash equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Bank balances
Call deposits
Bank overdrafts
Other US dollar accounts
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
10 | P a g e
Current quarter
$A’000
Previous quarter
$A’000
124
595
77
1,457
3
722
3
1,537
31 December 2022
Quarterly Report
6.
Payments to related parties of the entity and their associates
6.1
Aggregate amount of payments to related parties and their associates included in item 1
Aggregate amount of payments to related parties and their associates included in item 2
6.2
Current quarter
$A'000
64
-
Note: Salaries for executive directors are allocated to both corporate and exploration activities. All directors deferred salary
and superannuation benefits in the first quarter and therefore the April-June Quarter resulted in payment of salaries and benefits for the entire six-month period.
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an explanation for, such payments.
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
7.2
7.3
7.4
Loan facilities
Credit standby arrangements
Other (Convertible Notes)
Total financing facilities
7.5
7.6
Unused financing facilities available at quarter end
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing facilities have been entered into or are proposed to be entered into after quarter end, include a
note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
8.1
8.2
Net cash from / (used in) operating activities (item 1.9)
(Payments for exploration & evaluation classified as investing activities) (item 2.1(d))
Total relevant outgoings (item 8.1 + item 8.2)
Cash and cash equivalents at quarter end (item 4.6)
Unused finance facilities available at quarter end (item 7.5)
Total available funding (item 8.4 + item 8.5)
8.3
8.4
8.5
8.6
8.7
$A’000
(815)
(815)
722
722
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
0.9
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as
“N/A.” Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: The Company expenditure on exploration will fall significantly following the
completion of the 2022 exploration programme and accordingly, will have sufficient
coverage of expenditures for 2 quarters
11 | P a g e
31 December 2022
Quarterly Report
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: The Company is reviewing its fund strategy.
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: As stated above, following the completion by the Company of its 2022 exploration programme in the December quarter expenditures are forecast to significantly decline which will be able to fund activities for two quarters.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
12 | P a g e
31 December 2022
Quarterly Report
Compliance statement
1
2
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
This statement gives a true and fair view of the matters disclosed.
Date:
30 January 2023
Authorised by: JM Madden (Company Secretary)
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the
board.” If it has been authorised for release to the market by a committee of your board of directors, you can insert here:
“By the [name of board committee – e.g. Audit and Risk Committee].” If it has been authorised for release to the market
by a disclosure committee, you can insert here: “By the Disclosure Committee.”
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out
as complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles
and Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the
financial records of the entity have been properly maintained, that this report complies with the appropriate accounting
standards and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the
basis of a sound system of risk management and internal control which is operating effectively.
13 | P a g e
31 December 2022
Quarterly Report
Tenement Holding in Madagascar
Tenement
Number
Name
Blocks
Holder
Equity
10430
Bekisopa PR
64
Iron Ore Corporation
Madagascar sarl
100%
27211
Bekisopa PR
128
Iron Ore Corporation
Madagascar sarl
100%
35827
Bekisopa PR
32
Iron Ore Corporation
Madagascar sarl
100%
3757
Bekisopa PRE
16
Randriamananjara
(Acquired under Sale &
Purchase Agreement)
100%
6595
Samelahy PR
98
Mineral Resources
Madagascar sarl
100%
13011
Samelahy PR
33
Mineral Resources
Madagascar sarl
100%
21910
Samelahy PR
3
Mineral Resources
Madagascar sarl
100%
16635
Tratramarina East PR
144
Universal Exploration
Madagascar sarl
100%
16637
Tratramarina East PR
48
Universal Exploration
Madagascar sarl
100%
17245
Tratramarina East PR
160
Universal Exploration
Madagascar sarl
100%
18379
Tratramarina West PRE
16
18891
Tratramarina West PRE
48
14 | P a g e
Rakotoarisoa
(Acquired under Sale &
Purchase Agreement)
Rakotoarisoa
(Acquired under Sale &
Purchase Agreement)
100%
100%
31 December 2022
Quarterly Report
Competent Person’s Statement
The data in this report that relates to Mineral Resource Estimates and Exploration Targets for the Bekisopa deposits is based on information evaluated by Mr Simon Tear who is a Member of The Australasian Institute of Mining and Metallurgy (MAusIMM) and who has sufficient experience relevant to the
style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the “JORC Code”). Mr Tear is a
Director of H&S Consultants Pty Ltd and he consents to the inclusion in the report of the Mineral Resource in the form and context in which they appear.
Competent Person’s Statement
The information in this statement that relates to Exploration Targets and Exploration Results is based
on information compiled by Mr Jannie Leeuwner – BSc (Hons) Pr.Sci.Nat. MGSSA and is a full-time
employee of Vato Consulting LLC. Mr. Leeuwner is a registered Professional Natural Scientist
(Pr.Sci.Nat. - 400155/13) with the South African Council for Natural Scientific Professions (SACNASP). Mr. Leeuwner has sufficient experience which is relevant to the style of mineralisation and
type of deposits under consideration and the activity being undertaken to qualify as a Competent Person as defined in the Note for Mining Oil & Gas Companies, June 2009, of the London Stock Exchange and the 2012 Edition of the ‘Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code). Mr. Leeuwner consents to the inclusion of the information
in this release in the form and context in which it appears.
Competent Person’s Statement
The information in this report that relates to Mineral Processing and related scientific and technical information, is based on, and fairly represents information compiled by Mr Paul Bibby. Mr Bibby is a
Metallurgist and Managing Director of Akora Resources Limited (AKO), as such he is a shareholder in
Akora Resources Limited. Mr Bibby is a Fellow of the Australasian Institute of Mining and Metallurgy
(FAusIMM). Mr Bibby has sufficient experience which is relevant to the styles of mineralisation and its
processing under consideration and to the activity which he is undertaking to qualify as a Competent
Person as defined in the JORC Code. Mr Bibby consents to the inclusion in this report of the matters
based on his information in the form and context in which it appears including analytical, test data and
mineral processing results.
15 | P a g e
31 December 2022
Quarterly Report
AKORA RESOURCES LIMITED
Top 20 Shareholders
As At 27 January 2023
Rank
Registered shareholder
Shares
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
CITICORP NOMINEES PTY LIMITED
MR NICHOLAS JOHN AXAM
TRAVIS ANDERSON
JOHN CHARLES TUMAZOS
HSBC GLOBAL CUSTODY NOMINEES UK LIMITED
JORDAN EQUITIES PTY LTD
EVANACHAN LIMITED
PAUL GERARD BIBBY
HSBC CUSTODY NOMINEES (AUSTRALIA) LIMITED
MRS SONIA SHARMA
DALESAM PTY LTD
CLINE MINING CORPORATION
MA BAYRAM LLAMAS & EL GARCIA BAYRAM
STEPHEN LESLIE FABIAN
MR DAVID YONAN
MR MICHAEL FRANCIS & MRS MARYANNE FRANCIS
INTERCONTINENTAL PTY LIMITED
CAITHNESS RESOURCES PTY LTD
MR RUSSELL NEIL CREAGH
JOHN MICHAEL MADDEN
7,062,747
4,532,697
3,473,855
3,353,486
2,732,743
1,990,000
1,811,628
1,584,758
1,366,167
1,107,069
1,010,000
981,492
895,729
893,636
837,261
830,000
762,500
708,260
679,999
662,344
9.78%
6.28%
4.81%
4.65%
3.79%
2.76%
2.51%
2.20%
1.89%
1.53%
1.40%
1.36%
1.24%
1.24%
1.16%
1.15%
1.06%
0.98%
0.94%
0.92%
Top 20 Sharehpolders
Remainder
Total number of shares on issue
37,276,371
34,913,839
72,190,210
51.64%
48.36%
100.00%
1,933,659
1,677,026
500,000
4,110,685
2.68%
2.32%
0.69%
5.69%
Directors holdings (both direct and indirect):
PG Bibby
JM Madden
MH Stirzaker
Percentage
PG Bibby excludes the holding of a related party defined under AASB 124
AKORA RESOURCES LIMITED
Top 20 Shareholders
As At 21 October 2022
Rank
Registered shareholder
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
CITICORP NOMINEES PTY LIMITED
HSBC CUSTODY NOMINEES (AUSTRALIA) LIMITED
NICHOLAS JOHN AXAM
TRAVIS ANDERSON
JOHN CHARLES TUMAZOS
JORDAN EQUITIES PTY LTD
EVANACHAN LIMITED
PAUL GERARD BIBBY
KLIP PTY LTD
SONIA SHARMA
DALESAM PTY LTD
CLINE MINING CORPORATION
MICHAEL FRANCIS & MARYANNE FRANCIS
STEPHEN LESLIE FABIAN
INTERCONTINENTAL PTY LIMITED
DAVID YONAN
CAITHNESS RESOURCES PTY LTD
JOHN MICHAEL MADDEN
ROCK COD INVESTMENTS PTY LTD
GEOFFREY STUART CROW
6,889,404
6,720,090
4,491,457
3,473,855
3,353,486
2,000,000
1,811,628
1,369,759
1,194,924
1,107,069
1,010,000
981,492
830,000
813,636
762,500
745,000
708,260
662,344
619,114
612,899
9.54%
9.31%
6.22%
4.81%
4.65%
2.77%
2.51%
1.90%
1.66%
1.53%
1.40%
1.36%
1.15%
1.13%
1.06%
1.03%
0.98%
0.92%
0.86%
0.85%
Top 20 Shareholders
Remaining
Total number of shares on issue
40,156,917
32,033,293
72,190,210
55.63%
44.37%
100.00%
1,933,659
1,677,026
500,000
4,110,685
2.68%
2.32%
0.69%
5.69%
Direct and indirect interests of directors:
PAUL GERARD BIBBY
JOHN MICHAEL MADDEN
MICHAEL HENRY STIRZAKER
16 | P a g e
Shares
Percentage
Share your feedback
Discover