Bekisopa Trenching Program Successfully Completed.
Highlights:
• AKORA has completed its site trenching program, part of its ongoing exploration
program, at the high-grade Bekisopa iron ore project, focused on further defining the
surface DSO mineralisation between the known southern and central planned mining
pits.
• A total of 339 metres of trenching has been completed, with 365 samples to be sent to
the ALS laboratory in Perth for analysis.
• Magnetic susceptibility data collected from all sample locations confirms iron
mineralisation across all trenches and provides early indications of mineral abundance.
• Surface field mapping has been completed across the large and prospective zones
between the southern and central mineral resource areas.
AKORA Resources Limited (ASX: AKO) (AKORA or Company) released a Pre-Feasibility Study
for the Bekisopa Direct Shipping Ore (DSO) Iron Ore Project1
in south central Madagascar in March
2025. As AKORA works towards detailed feasibility study activities it continues to make progress
with continued exploration activities.
The previously advised surface exploration trenching program2
has now been completed with 339
metres of lineal exploration completed to a maximum depth of 2 metres. The trenching exploration
program, at Bekisopa, is aimed at identifying the at or near surface DSO iron ore in the prospective
zone between the known mineral resource and reserve areas, being the PFS planned significant
southern pit and the smaller central pit. Surface visual indications suggest iron mineralisation is
present throughout this zone in which historical exploration from the 1950’s and 1960’s by the
French Geological Society identified surface mineralisation through trenches and pits.
AKORA Managing Director and CEO, Mr Peter Bird said, “the completion of our trenching and
mapping programs at Bekisopa marks another important step in advancing our understanding of
the high-grade DSO potential across the project. The visual results to date continue to
demonstrate consistent iron mineralisation between the southern and central resource areas,
reinforcing our confidence in the scale and quality of the Bekisopa deposit. We also note that an
1
ASX Announcement Bekisopa PFS, 31 March 2025
2
ASX Announcement Bekisopa Exploration Program 3 October 2025
info@akoravy.com
ACN 139 847 555
ASX: AKO
www.akoravy.com
Akora Resources Limited
PO Box 28
Ballarat Victoria 3350
Australia
2
additional 1 million tonnes of reserve has been valued at an additional US$21M through the PFS
study. We look forward to receiving the assay results, which will guide the next phase of our
exploration and development planning.”
“We believe Madagascar’s new administration delivers the stability and reform we need and the
appointment of the new Minster of Mines confirms a seriousness and technocratic shift that is
supported by international funding. Having satisfied the reporting requirements, the Company will
now focus on its submission for a mining licence application. This will unlock our project’s full
economic value for Madagascar.”
Madagascar in-country Update
Since the appointment of the Prime Minister Herintsalma Rajaonarivelo on 20 October 2025,
under President Colonel Michael Randrianirina, the Government of Madagascar has moved
quickly to restore stability and advance reforms. A 29 member cabinet, including 25 civilian
ministers, reflects a shift towards a more inclusive and technocratic government.
Key appointments include, Mr Carl Andriamparany as Minister of Mines and Strategic Resources,
a respected former Secretary General of the Ministry of Mines and Executive Secretary of the
Chambre des Mines de Madagascar.
International institutions, including the World Bank, IMF and European Union are closely
observing these developments, with renewed funding commitments from the EU signalling
Madagascar’s steady return to political and economic normalisation.
The Company looks forward to advancing its mining licence application with the new government,
having satisfied preliminary requirements.
Bekisopa DSO Exploration
AKORA has now completed its most recent round of exploration for the Bekisopa DSO exploration
program by completing surface mapping and the excavation of 339 metres of trenching in areas
that show positive signs of surface iron mineralisation.
The mapping of one historical trench and some pits across the Bekisopa tenement areas 1 and 2
have been completed (Figure 1). These historical excavations were completed by the French
Geological Society in the 1950’s and 1960’s. While some non-compliant assay results exist for
these locations AKORA undertook to verify the locations, clear and inspect the visual mineralisation
and take up to date GPS coordinates for future reference. Further to this work surface outcrop
mapping of likely DSO has been completed to add further detail to the site geological model and to
support future exploration activities.
The exploration program focused on the zone between the southern and central resource areas.
This area of approximately 1.5 kilometres strike length has a significant number of historical
exploration pits. Areas 1 and 2, as per Figure 1 below, were selected for the trenching program
based on surface magnetic mapping and the surface visual indications of likely outcropping DSO.
3
Figure 1 - Bekisopa Exploration Plan Areas 1 and 2
4
Figure 2 - Surface Magnetic Map Showing Areas 1 and 2
Surface mapping was completed over two areas identified north of the Southern Zone at
Bekisopa and a total of 0.31 sq km were mapped. Within Area 1 several magnetite-hematite
outcrop zones were identified.
Trenching
Trenching was completed within the two areas as detailed in Figure 4 and Figure 5. A total of
eight trenches were completed and 338.7 metres were manually excavated to a maximum of 2
metres deep. Within Area 1 seven trenches (BEKT001, BEKT002, BEKT003, BEKT004,
BEKT006, BEKT007 and BEKT008) and within Area 2 one trench (BEKT005) was completed.
These figures also show the location of the historical trenches and pits that were identified and
the surface geological profile.
5
Trenching coordinates are detailed as follows:
Trench_ID Utm38sX Utm38sY Elev_m Length_m Azm_deg Inc_deg
BEKT001 586,868 7,609,122 870 36.00 42 0
BEKT002 586,796 7,609,269 855 87.40 79 0
BEKT003 586,837 7,609,186 865 20.10 90 0
BEKT004 586,905 7,609,085 870 30.00 90 0
BEKT005 586,613 7,608,652 848 42.70 81 0
BEKT006 586,898 7,609,268 860 30.00 90 0
BEKT007 586,930 7,609,167 869 31.50 90 0
BEKT008 586,899 7,609,023 866 61.00 83 0
All trenches intersected iron mineralisation with lithologies comprising massive magnetite-
hematite, saprock of magnetite-hematite and saprock of magnetite-bearing gneisses. Trench
cross sections are detailed in Appendix 1. All trenches were logged and magnetic susceptibility
readings were taken (Appendix 2).
Figure 3 a) Massive Magnetite/Hematite at Trench BEKT006 (4.5 to 11.5m)
b) Massive Magnetite/Hematite at Trench BEKT007 (6.0 to 18.5m)
6
Figure 4 - Area 1 Trenching Layout
7
Figure 5 - Area 2 Trenching Layout
Trench geological logging identified the following lithological details for the exploration program.
Trench ID
From
(metres)
To
(metres)
Interval
(metres)
Lithology Magnetic Susceptibility 10-3SI
BEKT001 0.00 3.00 3.00 Saprock Hematite-Magnetite 90-758
3.00 5.00 2.00 Massive Hematite-Magnetite 109-729
5.00 12.50 7.50 Saprock Hematite-Magnetite 61-560
12.50 14.50 2.00 Massive Hematite-Magnetite 165-757
14.50 16.80 2.30 Saprock Magnetite-Hematite 486-1000>
16.80 17.70 0.90 Massive Magnetite-Hematite 901-1000>
17.70 36.00 18.30 Saprock Magnetite-Hematite 508-1000>
BEKT002 0.00 5.50 5.50 Saprock Magnetite-Hematite 197-751
5.50 13.70 8.20 Saprock Magnetite-Gneiss 588-1000>
13.70 19.00 5.30 Saprock Magnetite-Hematite 647-1000>
19.00 21.00 2.00 Saprock Magnetite-Gneiss 448-830
21.00 28.00 7.00 Saprock Magnetite-Hematite 448-1000>
28.00 40.60 12.60 Saprock Magnetite-Gneiss 239-823
40.60 42.00 1.40 Saprock Magnetite-Hematite 321-887
42.00 51.80 9.80 Saprock Magnetite-Gneiss 129-877
51.80 57.00 5.20 Saprock Magnetite-Hematite 236-1000>
57.00 59.00 2.00 Massive Magnetite-Hematite 511-1000>
59.00 60.20 1.20 Saprock Magnetite-Hematite 475-803
60.20 61.00 0.80 Massive Magnetite-Hematite 503-1000>
8
61.00 71.50 10.50 Saprock Magnetite-Hematite 592-1000>
71.50 72.20 0.70 Massive Magnetite-Hematite 634-1000>
72.20 86.00 13.80 Saprock Magnetite-Hematite 619-1000>
86.00 87.40 1.40 Saprock Magnetite-Gneiss 124-544
BEKT003 0.00 2.15 2.15 Saprock Magnetite-Gneiss 155-259
2.15 3.75 1.60 Saprock Hematite-Magnetite 133-299
3.75 9.50 5.75 Saprock Magnetite-Gneiss 89-459
9.50 15.90 6.40 Saprock Hematite-Magnetite 113-906
15.90 20.10 4.20 Saprock Magnetite-Gneiss 38-386
BEKT004 0.00 9.70 9.70 Saprock Hematite-Magnetite 11-733
9.70 20.70 11.00 Saprock Magnetite-Gneiss 230-742
20.70 28.50 7.80 Saprock Hematite-Magnetite 9-485
28.50 30.10 1.60 Saprock Magnetite-Gneiss 99-193
BEKT005 0.00 3.53 3.53 Ferruginous Zone 358-675
3.53 42.70 39.17 Saprock Magnetite-Gneiss 22-988
BEKT006 0.00 4.50 4.50 Saprock Magnetite-Gneiss 45-331
4.50 11.50 7.00 Massive Magnetite-Hematite 163-1000>
11.50 23.30 11.80 Saprock Magnetite-Hematite 26-961
23.30 25.40 2.10 Saprock Magnetite-Gneiss 15-209
25.40 26.70 1.30 Saprock Calc-Silicate 2-14
26.70 30.00 3.30 Saprock Gneiss 2-22
BEKT007 0.00 4.00 4.00 Ferruginous Zone 68-230
4.00 6.00 2.00 Saprock Magnetite-Gneiss 21-259
6.00 18.50 12.50 Saprock Hematite-Magnetite 15-675
18.50 20.70 2.20 Saprock Magnetite-Gneiss 10-52
20.70 21.70 1.00 Saprock Hematite-Magnetite 113-282
21.70 31.50 9.80 Saprock Magnetite-Gneiss 9-135
BEKT008 0.00 1.00 1.00 Saprock Magnetite-Gneiss 133-315
1.00 3.80 2.80 Saprock Magnetite-Hematite 204-1000>
3.80 11.20 7.40 Saprock Magnetite-Gneiss 75-281
11.20 13.40 2.20 Saprock Magnetite-Hematite 85-694
13.40 16.50 3.10 Saprock Magnetite-Gneiss 118-191
16.50 18.00 1.50 Massive Magnetite-Hematite 134-775
18.00 19.75 1.75 Saprock Magnetite-Gneiss 245-570
19.75 20.50 0.75 Saprock Magnetite-Hematite 568-1000>
20.50 38.40 17.90 Saprock Magnetite-Gneiss 99-273
38.40 39.40 1.00 Saprock Magnetite-Hematite 384-493
39.40 61.00 21.60 Saprock Magnetite-Gneiss 45-456
A total of 332 continuous horizontal channel samples were collected across the trenches, and
another 33 vertical channel samples within the trenches were selected additionally. A total of 365
samples will be sent to the OMNIS laboratory in Antananarivo for preparation, after which pulps
will be sent to ALS - an accredited laboratory, in Perth, West Australia for determination of total
iron and a standard “iron suite” of elements by XRF analyses.
9
AKORA has used geological mapping and magnetic susceptibility readings to support the
identification of potential DSO mineralisation. No samples have as yet been submitted for
assays.
Visual estimates of mineral abundance should never be considered a proxy or substitute for
laboratory analyses where concentrations or grades are the factor of principal economic interest.
Visual estimates also potentially provide no information regarding impurities or deleterious
physical properties relevant to valuations.
Results are expected early 2026.
This announcement has been authorised by AKORA Resources Limited’s Board of Directors.
For further information please contact:
Peter Bird
Managing Director
E: info@akoravy.com
www.akoravy.com
Competent Persons Statements
The information in this statement that relates to Exploration Targets and Exploration Results is based on
information compiled by Mr Jannie Leeuwner – BSc (Hons) Pr.Sci.Nat. MGSSA and is a full-time employee
of Vato Consulting LLC. Mr. Leeuwner is a registered Professional Natural Scientist (Pr.Sci.Nat. -
400155/13) with the South African Council for Natural Scientific Professions (SACNASP). Mr. Leeuwner
has sufficient experience which is relevant to the style of mineralisation and type of deposits under
consideration and the activity being undertaken to qualify as a Competent Person as defined in the Note for
Mining Oil & Gas Companies, June 2009, of the London Stock Exchange and the 2012 Edition of the
‘Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code).
Mr. Leeuwner consents to the inclusion of the information in this release in the form and context in which it
appears.
10
Cleaner iron ore for greener steel
AKORA Resources (ASX: AKO) is an Australian resources company focused on the development of four
high-grade iron ore projects in Madagascar.
The Company’s flagship Bekisopa Iron Ore Project has a 194.7 million tonne (Mt) Inferred JORC Resource
(ASX Announcement 11 April 2022) with very low impurities able to produce a premium-priced +68% Fe
concentrate. Direct Reduced Iron-Electric Arc Furnace technology which is used to make greener steel
without coal and considerably less carbon emissions requires iron ore grades of at least 67%.
(ASX Announcement – Bekisopa Scoping Study, 14 November 2023)
To generate cash in the near-term, AKORA is advancing plans at Bekisopa for a Stage1, 2Mt per annum
Mine with an initial six year life of mine, producing 61.6% Fe average grade lump and fine direct shipping
ore (DSO) for shipping to Blast Furnace steelmakers.
(ASX Announcement - Bekisopa Pre-Feasibility Study, 31 March 2025)
The Company confirms that it is not aware of any new information or data that materially affects the above and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have
not materially changed.
And further the Company confirms that all material assumptions underpinning the 2Mt per annum production target continue to apply
and have not materially changed.
11
Appendix 1 Cross Sections
12
13
14
15
Appendix 2 – Magnetic Susceptibility Results
MXDeposit strip logs showing trench lithologies logged and magnetic susceptibility results
16
17
18
19
20
21
22
23
Appendix 3 – JORC Tables
JORC Code, 2012 Edition - Table 1 - Bekisopa Project
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random
chips, or specific specialised industry standard
measurement tools appropriate to the minerals under
investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any
measurement tools or systems used.
• Aspects of the determination of mineralisation that are
Material to the Public Report.
• In cases where ‘industry standard’ work has been done
this would be relatively simple (eg ‘reverse circulation
drilling was used to obtain 1 m samples from which 3 kg
was pulverised to produce a 30 g charge for fire assay’). In
other cases more explanation may be required, such as
where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types
(eg submarine nodules) may warrant disclosure of detailed
information.
• Trenching program was undertaken, and trenches were manually
excavated perpendicular to the strike of the iron mineralisation trends.
• The trenches were geologically logged and systemically sampled by using
hammers/chisels. Horizontal samples were taken across the centre to base
of the trenches and vertical samples were taken on the wall of the trenches.
• Sample intervals varied between 1 to 2 meters, typical 3-10kg.
• Samples will be sent to a preparation laboratory (OMNIS) in Antananarivo,
Madagascar where samples will be oven dried, manually crushed to -2mm,
split twice through a 50/50 riffle splitter to obtain a representative sub-
sample of approx. 100g, and then pulverise that >85 % pass -75 μm.
(Pending)
• Pulp samples will be sent to an accredited laboratory (ALS) in Perth,
Australia for determination of total iron and a standard “iron suite” of
elements by XRF analyses using techniques ME-XRF21u for standard iron-
ore XRF analysis and method ME-GRA05 for LOI analysis. (Pending)
• QA/QC procedures applied with alternating standards and blanks inserted
every 20 samples, and four duplicates (field and lab) inserted every 100
samples.
Drilling
techniques
• Drill type (eg core, reverse circulation, open-hole hammer,
rotary air blast, auger, Bangka, sonic, etc) and details (eg
core diameter, triple or standard tube, depth of diamond
tails, face-sampling bit or other type, whether core is
oriented and if so, by what method, etc).
• No drilling was completed.
• Trenches were manually excavated using picks, shovels, crowbars etc with
dimensions of 1-1.5m in widths and up to 2m deep. A total of 8 trenches
(BEKT001 to BEKT008) were completed and 338.7 meters excavated.
24
Criteria JORC Code explanation Commentary
Drill sample
recovery
• Method of recording and assessing core and chip sample
recoveries and results assessed.
• Measures taken to maximise sample recovery and ensure
representative nature of the samples.
• Whether a relationship exists between sample recovery
and grade and whether sample bias may have occurred
due to preferential loss/gain of fine/coarse material.
• No drilling was completed.
• Trench sample material was collected using rock pick hammers and chisels
to create continuous channels (10 cm wide and 5 cm deep). Horizontal
samples were taken across the centre to base of the trenches and vertical
samples were taken on the wall of the trenches
Logging • Whether core and chip samples have been geologically
and geotechnically logged to a level of detail to support
appropriate Mineral Resource estimation, mining studies
and metallurgical studies.
• Whether logging is qualitative or quantitative in nature.
Core (or costean, channel, etc) photography.
• The total length and percentage of the relevant
intersections logged.
• No drilling was completed.
• A set of standard operating procedures for trenching and sampling were
prepared by the company and Vato Consulting, who supervises the
program, and these are always adhered to.
• All trenches are logged quantitatively using industry standard practice on
site in enough detail to allow mineral resource estimates as required.
• Logging included: primary lithology, secondary lithology, weathering,
colour, grain size, texture, mineralisation type (generally magnetite or
hematite), mineralisation style, mineralisation %, structure, magnetic
susceptibility (see below), notes (longhand).
• All trenches are photographed.
• All trenches are logged using a ZH-SM30 magnetic susceptibility meter to
enable accurate distinction of iron (magnetite) rich units and to potentially
differentiate between magnetite and hematite rich mineralisation. Readings
recorded in 25cm intervals.
• Density measurements are made using the Archimedes method (mainly
fresh competent rock).
• All trenches logged in their entirety.
Sub-
sampling
techniques
and sample
preparation
• If core, whether cut or sawn and whether quarter, half or all
core taken.
• If non-core, whether riffled, tube sampled, rotary split, etc
and whether sampled wet or dry.
• For all sample types, the nature, quality and
appropriateness of the sample preparation technique.
• Quality control procedures adopted for all sub-sampling
stages to maximise representivity of samples.
• No drilling was completed.
• A set of standard operating procedures for trenching and sampling were
prepared by the company and Vato Consulting, who supervises the
program, and these are always adhered to.
• Samples will be prepared at the OMNIS laboratory in Antananarivo and
samples will be oven dried, crushed to -2mm, split twice through a 50/50
riffle splitter to obtain a representative sub-sample, weighing approx. 100g
25
Criteria JORC Code explanation Commentary
• Measures taken to ensure that the sampling is
representative of the in situ material collected, including for
instance results for field duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of
the material being sampled.
and then pulverized that 85% pass -75µm. (Pending)
• 1-2m sampling is deemed to be comprehensive and representative for the
style/type of mineralisation under investigation.
Quality of
assay data
and
laboratory
tests
• The nature, quality and appropriateness of the assaying
and laboratory procedures used and whether the technique
is considered partial or total.
• For geophysical tools, spectrometers, handheld XRF
instruments, etc, the parameters used in determining the
analysis including instrument make and model, reading
times, calibrations factors applied and their derivation, etc.
• Nature of quality control procedures adopted (eg
standards, blanks, duplicates, external laboratory checks)
and whether acceptable levels of accuracy (ie lack of bias)
and precision have been established.
• Pulp samples will be sent to ALS an accredited laboratory, in Perth, West
Australia for determination of total iron and a standard “iron suite” of
elements by XRF analyses using techniques ME-XRF21u for standard iron-
ore XRF analysis and method ME-GRA05 for LOI analysis. (Pending)
• QA/QC inhouse procedures applied with alternating standards and blanks
inserted every 20 samples, and four duplicates (field and lab) inserted
every 100 samples, in addition to the internal QAQC from the laboratory.
• OREAS standards OREAS40 / OREAS401 / OREAS404 / OREAS701 and
AMIS blank AMIS855 will be used for inhouse QAQC. (Pending)
• Standards, blanks, field and lab duplicates for trench sample analyses.
(Pending)
Verification
of sampling
and
assaying
• The verification of significant intersections by either
independent or alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures,
data verification, data storage (physical and electronic)
protocols.
• Discuss any adjustment to assay data.
• No drilling was completed.
• All trenching work was completed by Vato Consulting personnel and all
mineralised intervals were checked by Vato Consulting’s Principal
Geologist.
• All data was recorded on paper logs and after captured using Seequent
MXDeposit database software.
Location of
data points
• Accuracy and quality of surveys used to locate drill holes
(collar and down-hole surveys), trenches, mine workings
and other locations used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• No drilling was completed.
• Final trench locations have been completed using a handheld GPS
(GARMIN).
• The grid system used is UTM, WGS84, Zone 38 Southern Hemisphere
• An accurate topographic survey was completed in 2021 by FUTURMAP, a
local surveying consultant. The survey was conducted using PHANTOM 4
Pro type drones, and a pair of LEICA System 1200 dual frequency GPS. An
accuracy of 10mm horizontal and 20mm vertical is quoted.
26
Criteria JORC Code explanation Commentary
Data spacing
and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.
• Whether sample compositing has been applied.
• Data spacing nominally at 50-60m for the trenches within the mineralisation
zones.
• The data spacing and distribution is considered appropriate to establish
geological and grade continuity for the style of mineralisation.
• No sample compositing has been applied.
Orientation
of data in
relation to
geological
structure
• Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which this
is known, considering the deposit type.
• If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to
have introduced a sampling bias, this should be assessed
and reported if material.
• The ironstone unit has a strong north-south trend with a steep to shallow
westerly dip. The ironstone unit has a conspicuous regolith zone with
completely to highly weathered material up to 27m deep. The regolith hosts
iron mineralisation with enrich Direct Shipping Ore (DSO) parts.
• The trenches test the mineralisation in the regolith (weathered zone) and
enrich DSO parts.
• No sample known bias present.
Sample
security
• The measures taken to ensure sample security. • Chain of Custody procedures are implemented to document the possession
of the samples from collection through to storage, customs, export,
analysis, and reporting of results. Chain of custody forms are a permanent
records of sample handling and off-site dispatch.
• The on-site Geologist is responsible for the care and security of the
samples from the sample collection to the export stage. Samples prepared
during the day are stored in the preparation facility in labelled sealed plastic
bags.
• Samples will be delivered to the preparation laboratory and subsequent
analytical laboratory by courier.
Audits or
reviews
• The results of any audits or reviews of sampling
techniques and data.
• No audit has been conducted.
27
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria JORC Code explanation Commentary
Mineral
tenement
and land
tenure status
• Type, reference name/number, location and ownership
including agreements or material issues with third parties such
as joint ventures, partnerships, overriding royalties, native title
interests, historical sites, wilderness or national park and
environmental settings.
• The security of the tenure held at the time of reporting along
with any known impediments to obtaining a licence to operate in
the area.
• The Company completed the acquisition of the minority interest in Iron
Ore Corporation of Madagascar sarl held by Cline Mining Corporation
on 5 August 2020.
• The Company holds through Iron Ore Corporation of Madagascar sarl,
Universal Exploration Madagascar sarl and a Farm-in Agreement 12
exploration permits in three geographically distinct areas. All
administration fees due and payable to the Bureau du Cadastre Minier
de Madagascar (BCMM) have been and accordingly, all tenements are
in good standing with the government.
• The tenements are set out in the below
Exploration
done by
other parties
• Acknowledgment and appraisal of exploration by other parties. • Exploration has been conducted by UNDP (1976 - 78) and BRGM
(1958 - 62). Final reports on both episodes of work are available and
have been utilised in the recent IGR included in the Akora prospectus.
Airborne magnetics was flown for the government by Fugro and has
since been obtained, modelled and interpreted by Cline Mining and
Akora.
Geology • Deposit type, geological setting and style of mineralisation. • The tenure was acquired by AKO during 2014 and work since then has
consisted of:
o Data compilation and interpretation;
28
Criteria JORC Code explanation Commentary
o Confirmatory rock chip sampling (118 samples) and mapping;
o Re-interpretation of airborne geophysical data;
o Ground magnetic surveying (305 line km’s);
o The 2020 drilling program of 1095.5m diamond core drilling in
12 drillholes.
o The 2021 drilling program of 5117.02m diamond core drilling
in 52 drillholes.
o The 2022 drilling program of 1166.37m diamond core drilling
in 85 drillholes (BEKD064 to BEKD148).
o The 2023 drilling program of 967.3m diamond core drilling in
74 drillholes (BEKD149 to BEKD222).
o The 2024 drilling program of 508.01m diamond core drilling in
61 drillholes (BEKD0223 to BEKD283).
• The drilling has shown that the surface mineralisation continues at
depth, with at most a 25% increase in grade due to weathering effects.
However, it should be noted that some downslope creep of scree from
these units may exaggerate apparent width at surface.
• The mineralisation occurs as a series of magnetite bearing gneisses
and calc-silicates that occur as zones between 50m and 150m
combined true width.
• The mineralisation occurs as layers of massive magnetite (sometimes
altered to hematite) between 1m and 7m true width plus a lower grade
zone that consists of lenses, stringers, boudins and blebs of magnetite
aggregates that vary from 1cm to 10’s of cm wide within a calc-
silicate/gneiss unit (informally termed “coarse disseminated” here).
These units sometimes have an outer halo of finer disseminated
magnetite (informally termed “disseminated” here).
• This wide mineralisation halo provides a large tonnage potential over
the 6-7km strike of mapped mineralisation and associated magnetic
anomaly within the Akora tenement.
• The maiden MRE completed by H&S Consultants in 2022 is
29
Criteria JORC Code explanation Commentary
summarised as follows:
• The updated MRE completed by W&A Consultants in 2025 is
summarised as follows:
30
Criteria JORC Code explanation Commentary
Drill hole
Information
• A summary of all information material to the understanding of
the exploration results including a tabulation of the following
information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level
in metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
• If the exclusion of this information is justified on the basis that
the information is not Material and this exclusion does not
detract from the understanding of the report, the Competent
Person should clearly explain why this is the case.
• No further drilling was completed.
• All relevant drillhole information related to the
2020/2021/2022/2023/2024 drilling programs have been previously
reported