31 December 2023 Quarterly Activities & Cashflow Report
Released
Released
Announcement PDF
Akora Resources Ltd
ABN 90 139 847 555
ASX Code: AKO
Quarterly Report
30 September 2023
Quarterly
Report
For the quarter ended
31 December 2023
www.akoravy.com.au
Akora is developing a highgrade Direct Shipping Ore
(DSO) iron ore mine in
Madagascar.
This will be further developed
into serving the steel industry’s
accelerating focus on reducing
carbon dioxide (greenhouse
gas) emissions through
decarbonisation.
1|P a g e
Highlights
•
The Bekisopa Project Scoping Study shows
that the project could build to 2 million tonnes
per year of high-grade Direct Shipping Iron
Ore.
•
Pre-feasibility Study to start for the Bekisopa
DSO start-up project.
•
Significant iron mineralisation intercepts at
Bekisopa after completion of fourth drilling
campaign of 904.9m across 65 holes.
•
Magnetic survey completed at the near-by
Satrokala iron ore Project.
•
Appointment of new CFO/Company Secretary
and General Manager (Development)
strengthens executive team.
•
Post Quarter-end, the Company announced
the appointment of former BHP Iron Ore
President Mr Graeme Hunt as Chairman.
Bekisopa Iron Ore Project
Ownership 100% | Madagascar, Africa
The Bekisopa Iron Ore Project in Madagascar hosts an Inferred Resource of 194.7
million tonnes (Mt) with the potential to produce a quality Direct Ship Iron Ore product
and a premium grade 67.6% iron concentrate suitable for Direct Reduced Iron (DRI)
pellets for the steel industry’s accelerating decarbonisation.
An updated Scoping Study was released during the quarter and shows the Bekisopa
Iron Ore Project to be economically viable and could build to 2 million tonnes per year
of high-grade Direct Shipping Iron Ore.
Bekisopa Iron Ore Project in Madagascar is a major step closer to production after the
Company’s updated Scoping Study showed the project to be economically viable and could
build to an initial 2 million tonnes per annum (Mtpa) of DSO.
Prepared by Wardell Armstrong International (WAI), the Scoping Study was focused on a low
CAPEX option and utilising Bekisopa’s DSO JORC Indicated Resource of 4.4 million tonnes
(Mt) hosted in the project’s southern zone1. This Resource is contained in just 20% of the
project’s iron mineralisation strike length and offers the opportunity for further resources to be
identified and added to the Mine Plan with further drilling.
In this ’Low CAPEX Case’ open pit mining operation, the Study found that Bekisopa could
deliver an estimated initial five-year Mine Life with revenues of US$545 million for a C1
operating cost of US$45 per wet metric tonne (wmt) weighted average over the initial five
years (US$42/wmt at full production rate) and generate a pre-tax operating cash flow of
US$270 million.
The estimated upfront capital cost of US$55.3 million2 was based on using contractor labour,
mining equipment (excavators and trucks), mobile processing equipment (crushing and
screening plant) suitable for processing the iron ore into a high-grade 61% Fe average grade
lump and fines product. Contractors would also be used for truck hauling the products to port
and for ship loading to keep upfront capital costs contained.
Further, the Study also does not include any upside potential DSO tonnes from the
Company’s nearby Satrokala Project where around 30km of prospective strike length of iron
ore mineralisation exists. Exploration success at either Bekisopa and/or Satrokala, both
100% AKORA owned, would significantly add to this initial five-year DSO Start-Up Plan and
result in significantly improved Study financial outcomes.
Project Overview
The significant scale and particular mineralisation characteristics of Bekisopa’s iron ore
resource presents the Company with several staged development options over time:
1
Refer ASX Release date 11 April 2022 Maiden Resource Southern Zone
2
The US$55.3M is the “Low CAPEX Case” Contractor Operations / mobile crushing plant capital approach
2|P a g e
1.
Produce a 61% Fe average grade direct shipping ore (DSO): Mine, crush and screen
iron ore to produce a 61% Fe average grade lump and fines product for shipping to Blast
Furnace-Basic Oxygen Furnace (BF-BOF) steelmakers.
2.
Produce a +62% Fe grade DSO fines: Mine, crush and screen ore to produce a +62%
Fe grade fines product for shipping to BF-BOF steelmakers.
3.
Produce a premium-priced +68% Fe grade concentrate: Using cash generated from
Stages 1 and/or 2, add grinding and magnetic separation circuits to upgrade the ore to a
+68% Fe concentrate at 75 microns for shipping to Direct-Reduced iron (DRI-EAF)
steelmakers, where the use of coal is substituted for electricity and so making steel with
significant reductions in carbon emissions – what has been termed “green steel”.
A DSO lump and fines start-up operation using at-surface, weathered iron mineralisation
would need much less time, resources and capital to deliver to market. Positive cash flows
could be generated more quickly to repay the initial capital expenditure, fund further drilling
and resource development, as well as paying for processing improvements to produce higher
priced, higher grade products.
In Bekisopa’s southern zone, 4.4Mt of Indicated DSO tonnes has been defined according to
JORC standards within the overall total project resource of 194Mt. The Scoping Study
prepared by Wardell Armstrong International (WAI) was focused on a Low CAPEX option on
this DSO resource and presents two scenarios for comparison:
1.
A minimum capital ‘Low CAPEX Case’ DSO open pit mining operation which uses
contractor labour, mining equipment (trucks and loaders) and mobile processing
equipment (crushing, screen and conveying) suitable for processing the iron ore into a
61% Fe average grade lump and fines product. Contractors would also be used for truck
hauling the products to stockpiling location and for ship loading.
2.
A DSO open pit ”Low OPEX Case” mining operation which uses contract mining fleet
and labour and AKORA labour, as well as fixed equipment (crushing, screening and
conveying) suitable for processing the iron ore into a lump and fines product. AKORA
would also own and operate the on-road truck hauling fleet and to develop, own and
operate a dedicated port facility with ship loading infrastructure.
The company is now taking the Scoping Study forward and commencing a Pre-Feasibility
Study for the Bekisopa iron ore project and this will investigate in further detail the best
components of the Low Capex and Low Opex cases to determine the optimum project
design and operation.
3|P a g e
Figure 1. Bekisopa Iron Ore Project location with northern, central and southern zones
delineated. The Satrokala Project is located around 40km to the west of Bekisopa.
Figure 2. Low CAPEX Case highlights taken from the Bekisopa Scoping Study.
For both the Low CAPEX and Low OPEX cases studied in the Scoping Study, the production
schedule ramps up from 0.5 million tonnes per annum (Mtpa) to 2Mtpa over the initial five
years of mine life. This is to ensure that management and employees are progressively and
appropriately trained to reliably mine and process product of consistent quality, safely drive
haul trucks, and manage capital and operational scale-up risks. Opportunities exist to
4|P a g e
increase plant output and increase mine life through further development of the Company’s
nearby Satrokala Project, 40km to the south, or at Bekisopa where only 20% of the 6km
strike length of identified mineralisation has been shallow drilled for inclusion in this Study.
Notably, Bekisopa has iron ore outcropping at surface which is not included in the Scoping
Study numbers and could deliver an additional source of mined tonnes.
Resource growth potential
It is the Board’s expectation that future infill drilling at Bekisopa, including the Q3 2023 drilling
in the northern and central zones, will deliver additional Indicated DSO tonnes and therefore
extend the life of mine for high-grade DSO lump and fines production beyond this initial fiveyear plan.
It is also possible that the larger Satrokala project could add significant resources as well. In
2022, a rock chip program on the Satrokala tenements, around 40km to the south-west of
the main Bekisopa tenements, produced encouraging assay results. 102 rock chips showed
an average of 58.8% Fe and a subset of 66 rock chips had an average grade of 64.5% Fe
after excluding rocks at less than 58% Fe. Future drilling at Bekisopa and at Satrokala
(where a magnetic survey has recently been completed to confirm the extent of the magnetic
anomaly and to identify DSO drill targets) is expected to add suitable iron ore mineralisation
that could add additional years of DSO mining and production. Any future drilling and
exploration success as outlined could add significantly to the economic viability and
robustness of the Bekisopa Scoping Study DSO start-up approach.
Pre-feasibility Study to start for Direct Shipping High-Grade Iron Ore.
In December, AKORA announced it had advanced plans to develop the Bekisopa DSO startup project by starting a Pre-Feasibility Study (PFS) for the project, including building the
team to complete these projects.
The PFS will focus on the best operational and financial combination from the “low CAPEX”
and “Low OPEX” options which will utilise the project’s DSO JORC Indicated Resource of 4.4
million tonnes (Mt) hosted in the project’s southern zone.
WAI will conduct the PFS. The first modules of work will focus on defining the port options
and delivering an updated Mineral Resource Estimate which will include the recent 2023 infill
DSO drilling across Bekisopa’s northern and central zones.
Infill drilling campaign completed
During the quarter, the Company reported significant iron mineralisation intercepts at
Bekisopa after completing a fourth drilling campaign of 904.9m across 65 holes in August
2023.
Drilling on a 50m-by-50m grid across the project’s northern and central zones, iron ore
mineralisation intercepts averaged around 18.0m in the north, and 9.2m in the central
tenement.
Nine additional shallow drill holes were included below outcropping iron ore rock formations
in the Southern zone in an area to the east of the 2022 drilling campaign to test for a possible
mineralisation extension in that area.
All geological field logging has now been completed, and the iron ore mineralisation interval
samples were delivered to the OMNIS Laboratory in Antananarivo for preparation into assay
pulps. The assay pulps were then delivered to the ALS Iron Ore Technical Centre in Perth in
5|P a g e
three batches starting in December. The expectation is that all the assay results and an
updated Mineral Resource Estimate will be reported in Q1 2024.
Satrokala Iron Ore Project
Ownership 100% | Madagascar
Magnetic survey completed
During the quarter, an initial magnetic survey was completed at Satrokala. This magnetic
survey covered just 10km of the potential 30km of prospective iron mineralisation strike
length previously identified at the project. The target area was traversed on foot in 25m or
50m lines and in total traversing over ~610km. The results are due in Q1 2024 and will assist
in pinpointing exploratory holes for a maiden drilling program proposed in Q2 2024.
The survey was conducted using the same equipment and approach as employed at
Bekisopa in October 2019. Three magnetometer units were used and a team of seven
geologists walked the extent of the tenements under the supervision of Planetary
Geophysics, Australia. The magnetic survey data is now being assessed in Australia.
Figure 3. AKORA geologist team preparing for the Satrokala magnetic survey and walking
across the tenements and the rich red iron ground.
6|P a g e
Corporate
Cash Position
Akora Limited held cash reserves at the end of quarter of approximately $1.3 million.
Shareholder Information
As at 31 December 2023, the Company had 656 shareholders and 94,982,814 ordinary fully
paid shares on issue with the top 20 shareholders holding 58.25% of the total issued capital.
ASX Additional Information
ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure spend during the quarter
was $196,000. Full details of exploration activity during the quarter are set out in this report.
ASX Listing Rule 5.3.2: The Company confirms that there was no mine production and
development activities during the quarter.
ASX Listing Rule 5.3.5: Payment to related parties of the Company during the quarter was
$111,226 in cash. A description of and explanation for payments to related parties and their
associates per Section 6.1 of the Appendix 5B following this Quarterly Activities Report is set
out in the below table.
Director Remuneration
Current Quarter
$
Managing Director fees
62,480
Non-Executive Director fees
30,000
Company Secretarial fees
8,960
Superannuation
9,786
Total
7|P a g e
111,226
Appointment of Chief Financial officer and Company Secretary
In December 2023, the Company announced it had appointed experienced mining company
executive Mr Shane Turner as Chief Financial Officer and Company Secretary, effective from
1 January 2024.
As a Chartered Accountant with over 35 years accounting and financial experience, Mr
Turner has served as a Non-Executive Director, Company Secretary (Co Sec) and Chief
Financial Officer (CFO) with Mozambique-focused heavy mineral sands company MRG
Metals Ltd (ASX:MRQ) since 2011, and as Co Sec and CFO for White Rock Minerals Ltd
(ASX:WRM) since 2016.
Outgoing CFO and Co Sec, Mr John Madden, whose retirement was announced in August,
will continue to serve the Company until the 2023 year-end accounts and Annual Report are
completed in early 2024. The Company acknowledges and thanks John for his contribution
and guidance since establishing the company in 2009.
Appointment of General Manager – Development
In January 2024, subsequent to the end of the quarter, AKORA appointed mining operations
and project developer Mr Jason Whittle as General Manager - Development, effective from
15 January 2024. Jason has an Honors degree in Mineral Processing and has worked in
operational leadership roles throughout the mining value chain, in mining and processing,
through to marketing, before progressing to project development and implementation roles
on major projects across Australia, Peru and Africa, working for Pasminco, Zinifex, OZ
Minerals and MMG. Jason was most recently General Manager – Projects at Podium
Minerals covering resource development, study management with internal and external
resources, metallurgical testwork, financial modelling, environmental and license planning
and ESG.
Appointment of Chairman
In January 2024, subsequent to the end of the quarter, AKORA appointed former BHP Iron
Ore President Mr Graeme Hunt as Chairman, effective from 1 February 2024. Mr Hunt
started his 34-year career with BHP in the sinter plant at the Port Kembla steel works, before
performing General Management roles covering operations management, port operations,
and corporate strategy. Between 1999 to 2005, he was President BHP Iron Ore where his
global responsibilities spanned the expansion of BHP’s Pilbara operations and the
development of strong commercial relationships with Asian steel mills.
Mr Hunt served as Managing Director (MD) and Chief Executive Officer (CEO) of Lihir Gold
Ltd during which time he managed the company’s takeover by Newcrest Mining for A$9.5
billion.
More recently, he has held MD and CEO positions with both Broadspectrum (formerly
Transfield Services), and Chairman then MD and CEO of AGL Energy Ltd.
Mr Hunt’s commodity experience covers iron ore and steel, coal, manganese, aluminium,
copper, uranium, gold, electricity and gas while his management expertise spans steel
production, exploration, mining, logistics and port operations across Australia, South
America, PNG and West and Southern Africa.
8|P a g e
Board and Senior Management
Mike Stirzaker
Paul Bibby
Matthew Gill
Shane Turner
Non-executive Chairman with Graeme Hunt to assume the role from 1
February 2024
Managing Director & Chief Executive Officer
Non-executive Director
Chief Financial Officer and Company Secretary
ASX Announcement during the quarter
The following announcements were lodged on the ASX Market Announcements Platform
during the quarter:
Date
Description
11 October 2023
30 October 2023
2 November 2023
9 November 2023
14 November 2023
15 November 2023
13 December 2023
14 December 2023
Infill Drilling Programme Completed
September Quarterly Report
IMARC 2023 Conference Presentation
Satrokala Magnetic Survey Completed
Bekisopa Scoping Study
Presentation – Noosa Mining Conference
AKORA – Appoints CFO and Company Secretary
Starts Pre-Feasibility Study for DSO at Bekisopa
These announcements are available for viewing on the Company’s website
www.akoravy.com.
Other details
Head Office
12 Anderson Street West
Ballarat
Vic 3350
Website: www.akoravy.com
This announcement is authorised by the Board.
For further information contact:
Paul Bibby
Managing Director
Akora Resources
+ 61 (0) 419 449 833
paul.bibby@akoravy.com
9|P a g e
Matthew Lindh
Corporate Advisor
Harbury Advisory Pty Ltd
+ 61 (0) 432 363 933
mlindh@harbury.com.au
Gareth Quinn
Investor Relations
Republic PR
+ 61 (0) 417711108
gareth@republicpr.com.au
Competent Persons’ Statement
The information in this statement that relates to Exploration Targets and Exploration Results
is based on information compiled by Mr Jannie Leeuwner – BSc (Hons) Pr.Sci.Nat. MGSSA
and is a full-time employee of Vato Consulting LLC. Mr. Leeuwner is a registered
Professional Natural Scientist (Pr.Sci.Nat. - 400155/13) with the South African Council for
Natural Scientific Professions (SACNASP). Mr. Leeuwner has sufficient experience which is
relevant to the style of mineralisation and type of deposits under consideration and the
activity being undertaken to qualify as a Competent Person as defined in the Note for Mining
Oil & Gas Companies, June 2009, of the London Stock Exchange and the 2012 Edition of
the ‘Australian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’ (JORC Code). Mr. Leeuwner consents to the inclusion of the information in this
release in the form and context in which it appears.
The information in this report that relates to Mineral Processing and related scientific and
technical information, is based on, and fairly represents information compiled by Mr Paul
Bibby. Mr Bibby is a Metallurgist and Managing Director of Akora Resources Limited (AKO),
as such he is a shareholder in Akora Resources Limited. Mr Bibby is a Fellow of the
Australasian Institute of Mining and Metallurgy (FAusIMM). Mr Bibby has sufficient
experience which is relevant to the styles of mineralisation and its processing under
consideration and to the activity which he is undertaking to qualify as a Competent Person as
defined in the JORC Code. Mr Bibby consents to the inclusion in this report of the matters
based on his information in the form and context in which it appears including analytical, test
data and mineral processing results.
The information in this report that relates to Mineral Resources for the South Bekisopa Iron
Project is based on information prepared by Mr Richard Ellis BSc, MSc, MCSM, FGS, CGeol,
EurGeol and is a full-time employee of Wardell Armstrong International. Mr Ellis is a Chartered
Geologist of the Geological Society of London and has sufficient experience relevant to the
style of mineralisation, the type of deposit under consideration and to the activity undertaken to
qualify as a Competent Person as defined in the 2012 edition of the ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Ellis consents to
the inclusion of the information in the release in the form and context in which they appear.
10 | P a g e
Tenement Interests
As at 31 December 2023, the Company had interests in the following tenements (as required
by Listing Rule 5.3.3). There were no changes in the Company’s interests in tenements
during the quarter.
Project
Location
Tenement Number
Blocks
Bekisopa PR
Madagascar, Africa
10430
64
100%
Bekisopa PR
Madagascar, Africa
27211
128
100%
Bekisopa PR
Madagascar, Africa
35827
32
100%
Bekisopa PRE
Madagascar, Africa
3757
16
100%
Samelahy PR
Madagascar, Africa
6595
98
100%
Samelahy PR
Madagascar, Africa
13011
33
100%
Samelahy PR
Madagascar, Africa
21910
3
100%
Madagascar, Africa
16635
144
100%
Madagascar, Africa
16637
48
100%
Madagascar, Africa
17245
160
100%
Madagascar, Africa
18379
16
100%
Madagascar, Africa
18891
48
100%
Tratramarina East
PR
Tratramarina East
PR
Tratramarina East
PR
Tratramarina West
PRE
Tratramarina West
PRE
11 | P a g e
Current Interest
Mineral Resources and Ore
Reserves
Akora’s Resource at 31 December 2023
12 | P a g e
Company Profile
Akora Resources (ASX: AKO) is an exploration company engaged in the exploration and
development of the Bekisopa, Satrokala, Tratramarina and Ambodilafa Projects, all iron ore
prospects in Madagascar where the company holds 308km2 of tenements across these four
prospective exploration areas.
The Bekisopa Iron Ore Project is a high-grade iron ore project with an ~6km strike length and
an Inferred Resource of 194.7 million tonnes. Bekisopa has outcropping and weathered zone
Direct Shipping Ore (DSO) iron ore and has the potential to produce a premium grade +68%
iron concentrate suitable for Direct Reduced Iron pellets for a green steel future.
13 | P a g e
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
AKORA Resources Limited
ABN
Quarter ended (“current quarter”)
90 139 847 555
31 December 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
1.2
Receipts from customers
Payments for
(a) exploration & evaluation
(b) development
(c) production
(d) staff costs
(e) administration and corporate costs
Dividends received (see note 3)
Interest received
Interest and other costs of finance paid
Income taxes paid
Government grants and tax incentives
Other
(Cash Boost from Commonwealth
Government)
Net cash from / (used in) operating
activities
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
(e) investments
(f) other non-current assets
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
Cash flows from loans to other entities
Dividends received (see note 3)
2.2
2.3
2.4
14 | P a g e
Year to date
(12-months)
$A’000
-
-
(196)
(1,425)
(80)
(185)
(350)
(1,057)
2
5
(459)
(2,827)
Consolidated statement of cash flows
2.5
2.6
Other
Net cash from / (used in) investing
activities
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
Proceeds from issue of convertible debt
securities
Proceeds from exercise of options
Transaction costs related to issues of equity
securities or convertible debt securities
Proceeds from borrowings
Repayment of borrowings
Transaction costs related to loans and
borrowings
Dividends paid
Other (provide details if material)
Net cash from / (used in) financing
activities
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
Net cash from / (used in) operating
activities (item 1.9 above)
Net cash from / (used in) investing activities
(item 2.6 above)
Net cash from / (used in) financing activities
(item 3.10 above)
Effect of movement in exchange rates on
cash held
Cash and cash equivalents at end of
period
4.2
4.3
4.4
4.5
4.6
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Year to date
(12-months)
$A’000
-
-
-
3,579
-
(157)
-
3,422
1,776
722
(459)
(2,827)
-
-
-
3,422
(3)
(3)
1,314
1,314
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in
the consolidated statement of cash
flows) to the related items in the
accounts
5.1
5.2
5.3
5.4
5.5
Bank balances
Call deposits
Bank overdrafts
Other US dollar accounts
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
15 | P a g e
19
1,200
29
1,701
95
1,314
46
1,776
6.
Payments to related parties of the entity and their
associates
6.1
6.2
Current quarter
$A'000
Aggregate amount of payments to related parties and their
associates included in item 1
Aggregate amount of payments to related parties and their
associates included in item 2
111
-
Note: Salaries for executive directors are allocated to both corporate and exploration activities.
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
7.
Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
Add notes as necessary for an understanding of
the sources of finance available to the entity.
7.1
7.2
7.3
7.4
Loan facilities
Credit standby arrangements
Other (Convertible Notes)
Total financing facilities
7.5
7.6
Unused financing facilities available at quarter end
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
$A’000
8.
Estimated cash available for future operating activities
8.1
8.2
8.3
8.4
8.5
8.6
8.7
Net cash from / (used in) operating activities (item 1.9)
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
Total relevant outgoings (item 8.1 + item 8.2)
Cash and cash equivalents at quarter end (item 4.6)
Unused finance facilities available at quarter end (item 7.5)
Total available funding (item 8.4 + item 8.5)
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
(459)
(459)
1,314
1,314
2.9
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A.”
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating cash
flows for the time being and, if not, why not?
Answer: N/A.
16 | P a g e
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further cash to
fund its operations and, if so, what are those steps and how likely does it believe that they
will be successful?
Answer: N/A
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
17 | P a g e
For the quarter ended 31 December 2023
18
Compliance statement
1
2
This statement has been prepared in accordance with accounting standards and policies which comply with Listing
Rule 19.11A.
This statement gives a true and fair view of the matters disclosed.
Date:
31 January 2024
Authorised by:
Board of directors
(Name of body or officer authorising release – see note 4)
Notes
1.
2.
3.
4.
5.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s activities for the
past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose additional information
over and above the minimum required under the Listing Rules is encouraged to do so.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB
6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly cash flow report
has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent
standards apply to this report.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the
accounting policy of the entity.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board.” If it has been authorised
for release to the market by a committee of your board of directors, you can insert here: “By the [name of board committee – e.g. Audit and Risk
Committee].” If it has been authorised for release to the market by a disclosure committee, you can insert here: “By the Disclosure Committee.”
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying with
recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and Recommendations, the board should have
received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been properly maintained, that this
report complies with the appropriate accounting standards and gives a true and fair view of the cash flows of the entity, and that their opinion has
been formed on the basis of a sound system of risk management and internal control which is operating effectively.
18 | P a g e